[2019] KEHC 12421 (KLR)

[2019] KEHC 12421 (KLR)

The court found that there was a valid arbitration agreement between the parties and that the dispute regarding the alleged unlawful termination of the contracts and the calling of guarantees was properly referable to arbitration. The court held that its role was not to determine the merits of the termination or...

Source-derived case information.

Citation
[2019] KEHC 12421 (KLR)
Parties
Applicant: Civicon Limited; Respondent: Kenya Rural Roads Authority
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Miscellaneous Cause 265 of 2018
Procedural Posture
Miscellaneous Application / Ruling on Interim Injunction Pending Arbitration
Outcome
Interim injunction granted for 60 days to preserve status quo pending arbitration; each party to bear its own costs.
Judges
MM Kasango
Legal Topics
Interim Injunctions, Arbitration Agreements, Performance Guarantees, Public Procurement Contracts
Source Language
en
Commercial and Corporate Civil Procedure Interim Injunctions Arbitration Agreements Performance Guarantees Public Procurement Contracts

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 4 Party arguments 2 Amounts and remedies 8
Sign in to unlock

Parties

Civicon Limited

Applicant

Kenya Rural Roads Authority

Respondent

Procedural Posture

Miscellaneous Application / Ruling on Interim Injunction Pending Arbitration

  1. 1 Whether the court should grant interim injunctive relief restraining the defendant from terminating or assigning the contracts pending arbitration.
  2. 2 Whether the defendant should be restrained from calling or making demands on the plaintiff's performance and advance payment guarantees pending arbitration.
  3. 3 Whether the requirements for interim measures under section 7 of the Arbitration Act are satisfied.

Ratio Decidendi

The court found that there was a valid arbitration agreement between the parties and that the dispute regarding the alleged unlawful termination of the contracts and the calling of guarantees was properly referable to arbitration. The court held that its role was not to determine the merits of the termination or performance issues, but to preserve the status quo pending arbitration. The requirements for interim measures under section 7 of the Arbitration Act were satisfied, as there was a real threat to the subject matter of the arbitration and the plaintiff risked irreparable harm if the contracts were terminated or the guarantees called before the arbitral tribunal could address the...

Court Disposition

Interim injunction granted for 60 days to preserve status quo pending arbitration; each party to bear its own costs.

Orders

  • An injunction is issued for 60 days restraining the defendant from terminating, retendering, or assigning the benefit of Contract No. RWC 343 and from interfering with related assets at the Eldoret project site.
  • An injunction is issued for 60 days restraining the defendant from terminating, retendering, or assigning the benefit of Contract No. RWC 314 and from interfering with related assets at the Makueni project site.