[2009] KEHC 1092 (KLR)

[2009] KEHC 1092 (KLR)

The court found that the defendant, through its own engineer's certificates and written correspondence, admitted liability for the sum of Kshs.49,914,552/-. The defendant's proposal for a payment schedule and partial payments made towards the certified sum constituted clear admissions of the debt. The court held...

Source-derived case information.

Citation
[2009] KEHC 1092 (KLR)
Parties
Plaintiff: Clearspan Construction (A) Limited; Defendant: East African Gas Company Limited
Court
High Court
Court Station
High Court at Mombasa
Jurisdiction
Kenya
Case Number
Civil Case 1 of 2004
Procedural Posture
Civil Case / Ruling on Application for Summary Judgment and Striking Out Defence
Outcome
summary judgment for the plaintiff
Legal Topics
Construction Contracts, Summary Judgment, Admissions in Pleadings, Engineer Certification, Payment Certificates
Source Language
en
Commercial and Corporate Civil Procedure Construction Contracts Summary Judgment Admissions in Pleadings Engineer Certification Payment Certificates

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 4 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Clearspan Construction (A) Limited

Plaintiff

East African Gas Company Limited

Defendant

Procedural Posture

Civil Case / Ruling on Application for Summary Judgment and Striking Out Defence

  1. 1 Whether the defendant's defence should be struck out for being unmeritorious and raising no triable issues.
  2. 2 Whether summary judgment should be entered for the plaintiff based on admissions and certified payment certificates.
  3. 3 Whether the defendant admitted liability for the sum claimed by the plaintiff through correspondence and conduct.

Ratio Decidendi

The court found that the defendant, through its own engineer's certificates and written correspondence, admitted liability for the sum of Kshs.49,914,552/-. The defendant's proposal for a payment schedule and partial payments made towards the certified sum constituted clear admissions of the debt. The court held that the defence did not raise any triable issues, as there was no evidence of contesting the certificates or the authority of the engineer, and allegations of collusion or conspiracy were unparticularized and thus legally insufficient. The court further held that the claim for interest prior to suit was not proved or agreed upon and would not be allowed, but interest at court...

Court Disposition

summary judgment for the plaintiff

Orders

  • Summary judgment is entered for the plaintiff against the defendant in the sum of Kshs.49,914,552/-.
  • Interest at court rates is awarded on the principal sum from the date of filing suit until payment in full.