[2023] KEHC 24141 (KLR)

[2023] KEHC 24141 (KLR)

The court found that the plaintiff failed to prove that the defendant was in breach of the sale agreement. The delay in completion was attributable to the plaintiff's failure to discharge the property from encumbrance within the stipulated period, which was a condition precedent to completion. The defendant...

Source-derived case information.

Citation
[2023] KEHC 24141 (KLR)
Parties
Plaintiff: Clonbrook Properties Limited; Defendant: Dave Flowers Limited
Court
High Court
Court Station
High Court at Mombasa
Jurisdiction
Kenya
Case Number
Civil Case 3 of 2021
Procedural Posture
Civil Case / Judgment
Outcome
suit dismissed with costs to the defendant
Judges
DKN Magare
Legal Topics
Sale of Land, Breach of Contract, Specific Performance, Contractual Interest, Completion Notice, Pleading Requirements
Source Language
en
Commercial and Corporate Land and Property Sale of Land Breach of Contract Specific Performance Contractual Interest Completion Notice Pleading Requirements

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 5 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

Clonbrook Properties Limited

Plaintiff

Dave Flowers Limited

Defendant

Procedural Posture

Civil Case / Judgment

  1. 1 Whether the defendant was in breach of the sale agreement for delay in completion and liable to pay contractual interest.
  2. 2 Whether the plaintiff complied with all conditions precedent and issued the requisite completion notice before claiming interest for delay.
  3. 3 Whether the plaintiff strictly pleaded and proved the alleged special damages (interest for delay).

Ratio Decidendi

The court found that the plaintiff failed to prove that the defendant was in breach of the sale agreement. The delay in completion was attributable to the plaintiff's failure to discharge the property from encumbrance within the stipulated period, which was a condition precedent to completion. The defendant completed payment within 7 days of receiving the registered transfer, and there was no evidence of breach on their part. Furthermore, the plaintiff did not issue the requisite 21-day completion notice as required by the agreement, nor did they plead or prove the specific dates of breach or the calculation of the alleged interest. The court emphasized that special damages, such as...

Court Disposition

suit dismissed with costs to the defendant

Orders

  • The entire suit is dismissed with costs to the defendant.
  • The defendant shall have costs of Mombasa HCCA 132 of 2018 as directed in that appeal.