The court found that both parties agreed to refer the dispute to arbitration and that the subject matter—the project site, equipment, and materials—was under threat of interference. The court held that while interim measures of protection are appropriate to preserve the status quo pending arbitration, it must avoid...

Source-derived case information.

Citation
[2021] KEHC 253 (KLR)
Parties
Plaintiff: Coastal Kenya Enterprises Limited; Defendant: China City Construction International Engineering (Kenya) Co. Limited
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Commercial Civil Case E695 of 2021
Procedural Posture
Commercial Civil Case / Ruling on Interim Measures Pending Arbitration
Outcome
Plaintiff's application for interim measures partially allowed; Defendant's and Plaintiff's further applications dismissed; interim orders granted to preserve subject matter pending arbitration.
Judges
DAS Majanja
Legal Topics
Arbitration Agreements, Interim Measures of Protection, Mandatory Injunctions, Contract Termination, Subcontractor Rights
Source Language
en
Commercial and Corporate Civil Procedure Arbitration Agreements Interim Measures of Protection Mandatory Injunctions Contract Termination Subcontractor Rights

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 7 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Coastal Kenya Enterprises Limited

Plaintiff

China City Construction International Engineering (Kenya) Co. Limited

Defendant

Procedural Posture

Commercial Civil Case / Ruling on Interim Measures Pending Arbitration

  1. 1 Whether the court should grant interim measures of protection pending arbitration under section 7 of the Arbitration Act.
  2. 2 Whether the Defendant should be restrained from removing equipment and materials from the project site.
  3. 3 Whether the Plaintiff should provide security for use of the project site, equipment, and machinery.

Ratio Decidendi

The court found that both parties agreed to refer the dispute to arbitration and that the subject matter—the project site, equipment, and materials—was under threat of interference. The court held that while interim measures of protection are appropriate to preserve the status quo pending arbitration, it must avoid making conclusive findings that would prejudice the arbitral process. Given the involvement of a third party (Kenya Rural Roads Authority) and the public interest in the continuation of the road project, the court declined to grant mandatory orders for handover or exclusive possession. Instead, it allowed the Defendant limited access to the site for inspection and...

Court Disposition

Plaintiff's application for interim measures partially allowed; Defendant's and Plaintiff's further applications dismissed; interim orders granted to preserve subject matter pending arbitration.

Orders

  • Notice of Motion dated 11th November 2021 dismissed.
  • Notice of Motion dated 15th November 2021 dismissed.