[2021] KEHC 149 (KLR)

[2021] KEHC 149 (KLR)

The court found that while there were allegations of material non-disclosure and abuse of court orders by the plaintiff, the overriding consideration was the need to preserve the subject matter of the dispute—namely, the construction site and equipment—pending the determination of the main application and the...

Source-derived case information.

Citation
[2021] KEHC 149 (KLR)
Parties
Plaintiff: Coastal Kenya Enterprises; Defendant: China City Construction International Engineering (K) Ltd
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Suit E695 of 2021
Procedural Posture
Civil Suit / Interlocutory Application (ruling on Motion to Set Aside Injunctive Orders Pending Arbitration)
Outcome
Application declined; status quo maintained; parties restrained from construction; each party to bear own costs.
Judges
A Mabeya
Legal Topics
Injunctive Relief, Arbitration Agreements, Material Non Disclosure, Status Quo Orders, Contractual Disputes, Interim Measures
Source Language
en
Commercial and Corporate Civil Procedure Alternative Dispute Resolution Injunctive Relief Arbitration Agreements Material Non Disclosure Status Quo Orders Contractual Disputes +1 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 2 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Coastal Kenya Enterprises

Plaintiff

China City Construction International Engineering (K) Ltd

Defendant

Procedural Posture

Civil Suit / Interlocutory Application (ruling on Motion to Set Aside Injunctive Orders Pending Arbitration)

  1. 1 Whether the ex parte injunctive orders granted on 22/7/2021 should be set aside for material non-disclosure by the plaintiff.
  2. 2 Whether the plaintiff abused the court's orders by taking possession of the site and equipment.
  3. 3 Whether the status quo should be maintained pending arbitration and determination of the main application.

Ratio Decidendi

The court found that while there were allegations of material non-disclosure and abuse of court orders by the plaintiff, the overriding consideration was the need to preserve the subject matter of the dispute—namely, the construction site and equipment—pending the determination of the main application and the arbitral process. The court noted that both parties had contributed to the escalation of the dispute and that the public interest would be adversely affected by continued stoppage of the project. However, to prevent further abuse and to maintain fairness, the court declined to set aside the injunctive orders but ordered that the status quo as at 22/7/2021 be maintained, restraining...

Court Disposition

Application declined; status quo maintained; parties restrained from construction; each party to bear own costs.

Orders

  • The application to set aside the orders of 22/7/2021 is declined.
  • The status quo obtaining as at 22/7/2021 is to be maintained pending further orders on the application dated 19/7/2021.