[2024] KEHC 5810 (KLR)

[2024] KEHC 5810 (KLR)

The court found that the respondent's suit was not time-barred because the cause of action for breach of contract accrued when the respondent issued a demand letter in May 2017, not upon completion of the works in 2014. The suit, filed in April 2019, was within the statutory limitation period. The court held that a...

Source-derived case information.

Citation
[2024] KEHC 5810 (KLR)
Parties
Appellant: County Government Of Nyeri; Respondent: Nabaki Africa Constructions (K) Limited
Court
High Court
Court Station
High Court at Nyeri
Jurisdiction
Kenya
Case Number
Civil Appeal E023 of 2021
Procedural Posture
Civil Appeal / Judgment
Outcome
appeal_dismissed
Judges
MA Odero
Legal Topics
Public Procurement Contracts, Breach of Contract, Statutory Limitation Periods, Proof of Special Damages
Source Language
en
Commercial and Corporate Civil Procedure Public Procurement Contracts Breach of Contract Statutory Limitation Periods Proof of Special Damages

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 10 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

County Government Of Nyeri

Appellant

Nabaki Africa Constructions (K) Limited

Respondent

Procedural Posture

Civil Appeal / Judgment

  1. 1 Whether the respondent's suit was time-barred under Section 3(2) of the Public Authorities Act, Cap 39.
  2. 2 Whether there existed a valid and enforceable contract between the parties.
  3. 3 Whether the respondent performed the contracted works as alleged.

Ratio Decidendi

The court found that the respondent's suit was not time-barred because the cause of action for breach of contract accrued when the respondent issued a demand letter in May 2017, not upon completion of the works in 2014. The suit, filed in April 2019, was within the statutory limitation period. The court held that a valid and enforceable contract existed between the parties, evidenced by signed tender documents, a written agreement, and the issuance of an interim certificate. The respondent performed the contracted landscaping works, as confirmed by the Task Force report commissioned by the appellant. The appellant's allegations of fraud and forgery were unproven, as they were not...

Court Disposition

appeal_dismissed

Orders

  • The appeal is dismissed.
  • The award of Kshs. 6,084,650 to the respondent is upheld.