Mwaniki v Kenya Builders & Concrete Company Limited (Miscellaneous Application E408 of 2025) [2026] KEELRC 942 (KLR) (17 April 2026) (Ruling)
The application was filed outside the statutory limitation period of three years from the expiry of the ninety days allowed for payment, rendering it statute-barred and depriving the Court of jurisdiction to grant the orders sought.
Source-derived case information.
- Citation
- [2026] KEELRC 942 (KLR)
- Parties
- Applicant: Dancan Musyoka Mwaniki; Respondent: Kenya Builders & Concrete Company Limited
- Court
- Employment and Labour Relations Court
- Jurisdiction
- Kenya
- Case Number
- Miscellaneous Application E408 of 2025
- Procedural Posture
- Miscellaneous Application / Ruling
- Outcome
- Application struck off for being statute-barred.
- Legal Topics
- Work Injury Benefits, Statute of Limitations, Compensation Assessment, Enforcement of Director's Award
- Source Language
- en
Source-derived case record
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Dancan Musyoka Mwaniki
Applicant
Kenya Builders & Concrete Company Limited
Respondent
Procedural Posture
Miscellaneous Application / Ruling
Legal Issues
- 1 Whether the application to enforce the Director's compensation assessment is statute-barred
- 2 Whether the Applicant is entitled to adoption of the Director's assessment as a judgment
Ratio Decidendi
The application was filed outside the statutory limitation period of three years from the expiry of the ninety days allowed for payment, rendering it statute-barred and depriving the Court of jurisdiction to grant the orders sought.
Court Disposition
Application struck off for being statute-barred.
Orders
- Notice of Motion dated 21st October, 2025 struck off.
- No order as to costs.
Full Case Text
Judgment text and source record
1 paragraphs
Mwaniki v Kenya Builders & Concrete Company Limited (Miscellaneous Application E408 of 2025) [2026] KEELRC 942 (KLR) (17 April 2026) (Ruling) Neutral citation: [2026] KEELRC 942 (KLR) Republic of Kenya In the Employment and Labour Relations Court at Nairobi Miscellaneous Application E408 of 2025 AK Nzei, J April 17, 2026 Between Dancan Musyoka Mwaniki Applicant and Kenya Builders & Concrete Company Limited Respondent Ruling 1.The application before me for determination is the Applicant’s Notice of Motion dated 21st October, 2025. The Applicant seeks the following Orders:-a.That the compensation of Kshs.256,986.60 assessed by the Director of Occupational Safety and Health Services to the Applicant (sic) herein be adopted as a Judgment of this Court.b.That a decree be issued in accordance with the assessment of the Director Occupational Safety and Health for the sum of Kshs.256,986.60, with interest at 14% per annum from 25/10/2021.c.That costs of the application be paid by the Respondent. 2.The application is predicated on the Applicant’s supporting affidavit sworn on 21st October, 2025. It is deponed in the said supporting affidavit:-a.that the Applicant was on 19th January, 2021 cut by a machine motor chain while working for the Respondent, which resulted to an open would injury of his ring and middle fingers of the right hand.b.that the Applicant was treated at different hospitals, and was examined by Dr. M. Alfons of Coptic Hospital, whereupon DOSH FORM 1 was filled.c.that the matter was reported to the Director of Occupational Safety and Health Services, and DOSH/WIBA FORM 4 was duly filled. That the Applicant’s permanent incapacity was assessed at 12%, and compensation payable to him was assessed at Kshs.256,986.60.d.that the Director sent out a demand to the Respondent for payment on 25th October, 2021, but the Respondent adamantly refused to pay the aforesaid sum of Kshs.256,986.60; though he ought to have paid within 90 days of the claim under Section 26(4) of the Work Injury Benefits Act.e.that ninety days have lapsed since the demand, and that the Respondent did not prefer an appeal against the Director’s assessment. 3.Documents annexed to the supporting affidavit include copies of DOSH FORM 1, DOSH/WIBA FORM 4/demand for payment dated 25th October, 2021, and another demand notice by Applicant’s Advocates dated 1st October, 2025. 4.The Respondent did not file response to the application, though shown to have been served. The application is, therefore, unopposed. 5.I have noted from the aforementioned documents filed herein, and particularly DOSH/WIBA/FORM 4, that the Director of Occupational Safety and Health Services (Director) assessed the compensation payable to the Claimant (Kshs.256,986.60) on 25th October, 2021, and sent out a demand to the Respondent for payment of the assessed sum on the aforesaid date (25th October, 2021). The demand is contained in the DOSH/WIBA 4, which was addressed to the Respondent (the employer). 6.Section 26(4) provides that:-“(4)An employer or insurer against whom a claim for compensation is lodged by the Director under this Section, shall settle the claim within ninety days of lodging of the claim.” 7.Failure by the Respondent (the employer) to pay the assessed and demanded sum within the statutory period of ninety days amounted to an offence pursuant to Section 26(6) of WIBA and, vested a civil cause of action on the Applicant regarding the assessed sum. The said sum thus became the Applicant’s right arising from the employer-employee relationship (contract of service) between the Applicant and the Respondent. The present enforcement suit/application, therefore, ought to have been filed within three (3) years from the date of expiry of the ninety days’ period given to the Respondent by the Director to pay the assessed sum. 8.The aforesaid ninety days ran from 25th October, 2021 and lapsed on 25th January, 2022. The limitation period for filing suit (three years) started running as from 26th January, 2022. Section 89 (formerly Section 90) of the Employment Act provides as follows:-“Notwithstanding the provisions of Section 4(1) of the Limitation of Actions Act, no civil action or proceedings based or arising out of this Act or a contract of service in general shall lie or be instituted unless it is commenced within three years next after the act, neglect or default complained or in the case of continuing injury or damage within twelve months next after the cessation thereof.” 9.The present suit/application was filed on 24th October, 2025, approximately three years and ten months from the date the cause of action arose. The suit/application herein was clearly filed outside the time limited by statute for its filing and is, therefore, statute barred. 10.Although the orders sought by the Applicant would have been merited had the application herein been filed within the time prescribed by statute, this Court’s hands are now tied by the statute as it has no jurisdiction to grant orders based on a statute-barred suit. 11.In view of all the foregoing, the Notice of Motion dated 21st October, 2025 is hereby struck-off for being statute-barred, with no order as to costs. 12.It is so ordered. DATED, SIGNED AND DELIVERED AT NAIROBI THIS 17TH DAY OF APRIL 2026AGNES KITIKU NZEIJUDGEOrderThis Ruling has been delivered via Microsoft Teams Online Platform. A signed copy will be availed to each party upon payment of the applicable Court fees.Appearance:Mr. Masua for the ApplicantNo appearance for the Respondent