[2019] KEHC 8223 (KLR)

[2019] KEHC 8223 (KLR)

The court found that the plaintiff had established, on a balance of probabilities, that it performed its contractual obligations by designing, fabricating, and installing the agreed products, as evidenced by LPOs, quotations, completion certificates, and invoices. The defendant's allegations of breach, fraud, and...

Source-derived case information.

Citation
[2019] KEHC 8223 (KLR)
Parties
Plaintiff: David Engineering Limited; Defendant: Emirates Neon Group Kenya Ltd
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Case 488 of 2011
Procedural Posture
Civil Suit / Judgment
Outcome
Judgment for the plaintiff for Kshs.42,992,279/= plus interest at court rates from the date of filing suit until payment in full and costs of the suit.
Judges
F Tuiyott
Legal Topics
Breach of Contract, Special Damages, Contractual Interest, Right of Lien
Source Language
en
Commercial and Corporate Breach of Contract Special Damages Contractual Interest Right of Lien

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 2 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

David Engineering Limited

Plaintiff

Emirates Neon Group Kenya Ltd

Defendant

Procedural Posture

Civil Suit / Judgment

  1. 1 Was the suit filed without proper authority by the plaintiff company?
  2. 2 Did the defendant breach the contract with the plaintiff?
  3. 3 Has the plaintiff proved its claim for Kshs.42,992,279/= or any part thereof?

Ratio Decidendi

The court found that the plaintiff had established, on a balance of probabilities, that it performed its contractual obligations by designing, fabricating, and installing the agreed products, as evidenced by LPOs, quotations, completion certificates, and invoices. The defendant's allegations of breach, fraud, and collusion were not substantiated by evidence and were not specifically pleaded or proved. The court held that the plaintiff was entitled to the claimed sum, including the retention amount, as the period for its release had lapsed and the plaintiff was not to blame for any non-installation. The exercise of a right of lien by the plaintiff did not bar it from pursuing a civil claim...

Court Disposition

Judgment for the plaintiff for Kshs.42,992,279/= plus interest at court rates from the date of filing suit until payment in full and costs of the suit.

Orders

  • Judgment entered for the plaintiff against the defendant for Kshs.42,992,279/=
  • Interest awarded at court rates from the date of filing suit until payment in full