[2014] KEHC 3787 (KLR)

[2014] KEHC 3787 (KLR)

The court held that the application for enforcement was not vitiated by delay, as the intervening events were sanctioned by law and explained the time lapse. The court found that objections under section 37 of the Arbitration Act are not barred by res judicata at the enforcement stage unless previously determined....

Source-derived case information.

Citation
[2014] KEHC 3787 (KLR)
Parties
Applicant: Deekay Contractors Limited; Respondent: Construction & Contracting Limited
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Suit 762 of 2003
Procedural Posture
Miscellaneous Application / Ruling on Application for Leave to Enforce Arbitral Award
Outcome
Application allowed. Arbitral award recognized and enforced as a decree of the court. Costs awarded to the applicant.
Judges
F Gikonyo
Legal Topics
Arbitral Award Enforcement, Grounds for Refusal of Enforcement, Res Judicata in Arbitration, Right to Be Heard, Pleadings in Arbitration, Costs Award
Source Language
en
Alternative Dispute Resolution Civil Procedure Arbitral Award Enforcement Grounds for Refusal of Enforcement Res Judicata in Arbitration Right to Be Heard Pleadings in Arbitration Costs Award

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 6 Authorities cited 10 Party arguments 2
Sign in to unlock

Parties

Deekay Contractors Limited

Applicant

Construction & Contracting Limited

Respondent

Procedural Posture

Miscellaneous Application / Ruling on Application for Leave to Enforce Arbitral Award

  1. 1 Whether the arbitral award dated 19th July 2003 should be recognized and enforced as a decree of the court.
  2. 2 Whether the respondent is barred by res judicata from raising objections under section 37 of the Arbitration Act at the enforcement stage.
  3. 3 Whether the arbitral award was made in breach of the rules of natural justice or outside the scope of the reference.

Ratio Decidendi

The court held that the application for enforcement was not vitiated by delay, as the intervening events were sanctioned by law and explained the time lapse. The court found that objections under section 37 of the Arbitration Act are not barred by res judicata at the enforcement stage unless previously determined. Upon examining the arbitral record, the court determined that the issue of the architect's certificate was properly pleaded and addressed before the arbitrator, and the respondent had the opportunity to respond but chose not to. The court rejected the respondent's argument that the award was based on unpleaded or unheard matters, finding no breach of natural justice or excess of...

Court Disposition

Application allowed. Arbitral award recognized and enforced as a decree of the court. Costs awarded to the applicant.

Orders

  • The arbitral award dated 19th July 2003 is recognized and enforced as an order of this court under section 36 of the Arbitration Act.
  • The plaintiff's application is allowed with costs to be paid by the defendant.