[2018] KEHC 9098 (KLR)

[2018] KEHC 9098 (KLR)

The court found that the Plaintiff executed the contract works to completion under the supervision of the Project Architect and Project Manager. Although variations exceeding the contractual limit were made, the responsibility to seek prior approval lay with the Architect, not the Plaintiff. The Defendant failed to...

Source-derived case information.

Citation
[2018] KEHC 9098 (KLR)
Parties
Plaintiff: Dinesh Construction Limited; Defendant: Bamburi Cement Limited
Court
High Court
Court Station
High Court at Nairobi (Milimani Law Courts)
Jurisdiction
Kenya
Case Number
Civil Case 300 of 2015
Procedural Posture
Civil Case / Judgment
Outcome
Judgment for the Plaintiff.
Judges
OA Sewe
Legal Topics
Building Contracts, Contractual Variations, Final Certificates, Interest Awards, Limitation of Actions, Arbitration Clauses
Source Language
en
Commercial and Corporate Civil Procedure Building Contracts Contractual Variations Final Certificates Interest Awards Limitation of Actions Arbitration Clauses

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 14 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Dinesh Construction Limited

Plaintiff

Bamburi Cement Limited

Defendant

Procedural Posture

Civil Case / Judgment

  1. 1 Whether the variations to the contract works were valid and binding on the Defendant.
  2. 2 Whether the Plaintiff is entitled to the sum of Kshs. 19,082,192.88 as per the Revised Final Certificate.
  3. 3 Whether interest is payable on the outstanding sum and at what rate.

Ratio Decidendi

The court found that the Plaintiff executed the contract works to completion under the supervision of the Project Architect and Project Manager. Although variations exceeding the contractual limit were made, the responsibility to seek prior approval lay with the Architect, not the Plaintiff. The Defendant failed to prove that the variations were unauthorized or in breach of the contract. The parties held a consultative meeting, agreed on the re-measurement and revaluation of the works, and a Revised Final Certificate was issued and accepted by both parties. The Defendant's subsequent refusal to pay was unjustified, especially as it did not challenge the process or outcome of the...

Court Disposition

Judgment for the Plaintiff.

Orders

  • Judgment entered for the Plaintiff in the sum of Kshs. 19,082,192.88.
  • Interest at court rates on the sum of Kshs. 19,082,192.88 from 26 June 2010 until payment in full.