[2018] KEHC 2097 (KLR)

[2018] KEHC 2097 (KLR)

The High Court found that while the respondent did leave some construction material on site, the trial magistrate erred in relying solely on the respondent's demand letter to determine the quantity and value. The court considered the evidence of both parties and witnesses, concluding that only a limited quantity of...

Source-derived case information.

Citation
[2018] KEHC 2097 (KLR)
Parties
Appellant: Rev. Dominic Ochoo t/a Bala Mercy Children Centre (BMC); Respondent: James Odhiambo Oricho
Court
High Court
Court Station
High Court at Kisii
Jurisdiction
Kenya
Case Number
Civil Appeal 31 of 2016
Procedural Posture
Civil Appeal / Judgment
Outcome
Appeal allowed in part; judgment of subordinate court set aside and substituted.
Judges
DAS Majanja
Legal Topics
Construction Contracts, Breach of Contract, Quantum of Damages, Contractual Obligations
Source Language
en
Commercial and Corporate Civil Procedure Construction Contracts Breach of Contract Quantum of Damages Contractual Obligations

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 1 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Rev. Dominic Ochoo t/a Bala Mercy Children Centre (BMC)

Appellant

James Odhiambo Oricho

Respondent

Procedural Posture

Civil Appeal / Judgment

  1. 1 Whether the respondent was entitled to Kshs. 644,500/- for conversion of construction material left on site.
  2. 2 Whether the respondent was entitled to Kshs. 632,500/- for idle plant and equipment after completion of the contract.

Ratio Decidendi

The High Court found that while the respondent did leave some construction material on site, the trial magistrate erred in relying solely on the respondent's demand letter to determine the quantity and value. The court considered the evidence of both parties and witnesses, concluding that only a limited quantity of material was left and awarding compensation accordingly. Regarding the claim for idle plant and equipment, the court held that the contract did not require the respondent to remain on site after completion pending inspection, nor was there evidence that the respondent was prevented from removing his equipment. The claim for idle plant and equipment thus lacked contractual basis...

Court Disposition

Appeal allowed in part; judgment of subordinate court set aside and substituted.

Orders

  • Judgment entered for the respondent against the appellant for Kshs. 179,500/- with interest at court rates from the date of filing suit until payment in full.
  • The appellant shall pay costs of the suit in the subordinate court.