[2005] KEHC 1309 (KLR)

[2005] KEHC 1309 (KLR)

The court found that a valid contract existed between the parties, including all duly authorised variations, and that the defendant's allegations of illegality, fraud, or irregularity were unsubstantiated by credible evidence. The contract expressly provided for arbitration of disputes, and the plaintiff had not...

Source-derived case information.

Citation
[2005] KEHC 1309 (KLR)
Parties
Plaintiff: Don-Woods Company Ltd.; Defendant: Kenya Pipeline Company Ltd.
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Suit 1041 of 2004
Procedural Posture
Civil Suit / Interlocutory Application (injunction and Reference to Arbitration)
Outcome
Plaintiff's application allowed; injunction granted; dispute referred to arbitration; costs to plaintiff.
Legal Topics
Building Contracts, Contract Variation, Arbitration Clauses, Injunctive Relief, Termination of Contracts, Corporate Governance
Source Language
en
Commercial and Corporate Civil Procedure Alternative Dispute Resolution Building Contracts Contract Variation Arbitration Clauses Injunctive Relief Termination of Contracts +1 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 6 Authorities cited 20 Party arguments 2 Amounts and remedies 6
Sign in to unlock

Parties

Don-Woods Company Ltd.

Plaintiff

Kenya Pipeline Company Ltd.

Defendant

Procedural Posture

Civil Suit / Interlocutory Application (injunction and Reference to Arbitration)

  1. 1 Whether the contract between the parties was valid and enforceable at the time of the alleged breach.
  2. 2 Whether the dispute between the parties should be referred to arbitration under the contract's arbitration clause.
  3. 3 Whether the plaintiff is entitled to an interlocutory injunction to preserve the project site and assets pending determination of the suit or arbitration.

Ratio Decidendi

The court found that a valid contract existed between the parties, including all duly authorised variations, and that the defendant's allegations of illegality, fraud, or irregularity were unsubstantiated by credible evidence. The contract expressly provided for arbitration of disputes, and the plaintiff had not waived its right to arbitration. The defendant's refusal to proceed to arbitration was unjustified. The court held that the plaintiff had established a prima facie case for injunctive relief, as the nature of the works and assets at the project site made damages an inadequate remedy and the balance of convenience favoured preservation of the status quo. The defendant's internal...

Court Disposition

Plaintiff's application allowed; injunction granted; dispute referred to arbitration; costs to plaintiff.

Orders

  • An injunction is issued restraining the defendant from removing, dismantling, or interfering with the plaintiff's plant, machinery, equipment, building materials, or personnel at the project site pending hearing and determination of the suit.
  • The dispute between the parties is referred forthwith to arbitration as provided in clause 36 of the contract agreement and in terms of sections 6 and 7 of the Arbitration Act, 1995.