[2023] KEHC 18108 (KLR)

[2023] KEHC 18108 (KLR)

The court found that while the parties entered into a valid contract for the supply, installation, implementation, and commissioning of a budgeting system, the Plaintiff failed to complete the contract within the agreed and extended timelines and did not maintain a valid performance bond as required. The Defendant...

Source-derived case information.

Citation
[2023] KEHC 18108 (KLR)
Parties
Plaintiff: Doorsun Consulting Limited; Defendant: Kenya Pipeline Company Limited
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Commercial Case E073 of 2020
Procedural Posture
Commercial Case / Judgment
Outcome
suit dismissed
Judges
DAS Majanja
Legal Topics
Breach of Contract, Contractual Payments, Performance Bonds, Retention Clauses, Third Party Contracts, Damages and Costs
Source Language
en
Commercial and Corporate Civil Procedure Breach of Contract Contractual Payments Performance Bonds Retention Clauses Third Party Contracts Damages and Costs

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 2 Party arguments 2 Amounts and remedies 4
Sign in to unlock

Parties

Doorsun Consulting Limited

Plaintiff

Kenya Pipeline Company Limited

Defendant

Procedural Posture

Commercial Case / Judgment

  1. 1 Whether the Plaintiff and the Defendant entered into a contract for the supply, installation, implementation and commissioning of a budgeting system.
  2. 2 Whether the Plaintiff performed its obligations under the contract.
  3. 3 Whether the Defendant breached the contract by failing to pay the Plaintiff the software license fees, maintenance license fees, training costs and implementation costs as provided for in the contract.

Ratio Decidendi

The court found that while the parties entered into a valid contract for the supply, installation, implementation, and commissioning of a budgeting system, the Plaintiff failed to complete the contract within the agreed and extended timelines and did not maintain a valid performance bond as required. The Defendant was entitled under the contract to retain 10% of payments until project completion and resolution of all issues, which did not occur as the project never reached 'go-live' status. The Plaintiff's claims for withheld payments, maintenance fees, and VAT penalties were dismissed as the contractual conditions for payment were not met. The Defendant was not liable for the Plaintiff's...

Court Disposition

suit dismissed

Orders

  • The Plaintiff's suit is dismissed with costs to the Defendant.