[2011] KEHC 1575 (KLR)

[2011] KEHC 1575 (KLR)

The court held that the applicant was entitled to seek interim injunctive relief under Section 7 of the Arbitration Act, 1995, notwithstanding the existence of an arbitration agreement. The contract had not been repudiated or terminated, and the dispute resolution mechanism required the parties to continue with the...

Source-derived case information.

Citation
[2011] KEHC 1575 (KLR)
Parties
Plaintiff: Draft and Develop Engineers Ltd; Defendant: National Water Conservation and Pipeline Corporation
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Suit 11 of 2011
Procedural Posture
Civil Suit / Ruling on Interlocutory Injunction Application Under Section 7 of the Arbitration Act
Outcome
application allowed
Judges
CN Mugo
Legal Topics
Arbitration Interim Measures, Construction Contracts, Injunctive Relief, Contractual Disputes
Source Language
en
Commercial and Corporate Civil Procedure Arbitration Interim Measures Construction Contracts Injunctive Relief Contractual Disputes

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 3 Party arguments 2
Sign in to unlock

Parties

Draft and Develop Engineers Ltd

Plaintiff

National Water Conservation and Pipeline Corporation

Defendant

Procedural Posture

Civil Suit / Ruling on Interlocutory Injunction Application Under Section 7 of the Arbitration Act

  1. 1 Whether the applicant is entitled to interim injunctive relief under Section 7 of the Arbitration Act pending arbitration.
  2. 2 Whether the respondent's threatened actions constitute a breach or interference with the contract prior to the conclusion of the dispute resolution process.
  3. 3 Whether the dispute resolution mechanism under the contract ousts the jurisdiction of the court to grant interim measures.

Ratio Decidendi

The court held that the applicant was entitled to seek interim injunctive relief under Section 7 of the Arbitration Act, 1995, notwithstanding the existence of an arbitration agreement. The contract had not been repudiated or terminated, and the dispute resolution mechanism required the parties to continue with the works pending resolution of the dispute. The respondent's threat to take over the works and appoint another contractor, if carried out, would undermine the agreed dispute resolution process and potentially cause irreparable harm to the applicant. The court found that a prima facie case had been established, and that the balance of convenience and the risk of irreparable loss...

Court Disposition

application allowed

Orders

  • The respondent is restrained from terminating, breaching, or interfering with the contract pending arbitration.
  • The respondent is restrained from appointing another contractor or using the applicant's materials, plant, and equipment on site pending arbitration.