[2017] KECA 341 (KLR)

[2017] KECA 341 (KLR)

The Court of Appeal held that the trial court properly exercised its discretion in varying the consent decree and extending the completion period for the sale transaction. The court found that the appellant, East African Portland Cement Company Limited, failed to disclose material facts regarding the threatened...

Source-derived case information.

Citation
[2017] KECA 341 (KLR)
Parties
Appellant: East African Portland Cement Company Limited; Respondent: Superior Homes Limited
Court
Court of Appeal
Court Station
Court of Appeal at Nairobi
Jurisdiction
Kenya
Case Number
Civil Appeal 158 of 2014
Procedural Posture
Civil Appeal / Judgment
Outcome
appeal dismissed
Judges
J Wakiaga, RN Nambuye, GK Oenga
Legal Topics
Consent Judgments, Variation of Decree, Sale of Land, Material Non Disclosure, Contractual Obligations, Extension of Time
Source Language
en
Land and Property Civil Procedure Commercial and Corporate Consent Judgments Variation of Decree Sale of Land Material Non Disclosure Contractual Obligations +1 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 11 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

East African Portland Cement Company Limited

Appellant

Superior Homes Limited

Respondent

Procedural Posture

Civil Appeal / Judgment

  1. 1 Whether the High Court correctly exercised its discretion in varying a consent decree and extending time for completion of a sale transaction.
  2. 2 Whether there were sufficient grounds to vary the terms of a consent order as to time for completion based on alleged non-disclosure of material facts.
  3. 3 Whether the provision of a bank facility letter instead of a bank guarantee satisfied the requirements of the consent decree.

Ratio Decidendi

The Court of Appeal held that the trial court properly exercised its discretion in varying the consent decree and extending the completion period for the sale transaction. The court found that the appellant, East African Portland Cement Company Limited, failed to disclose material facts regarding the threatened compulsory acquisition and possible revocation of title to the property, which were known to it but not to the respondent, Superior Homes Limited, at the time of entering into the consent decree. This non-disclosure constituted sufficient grounds for varying the terms of the consent order as to time for completion. The court further determined that the provision of a bank facility...

Court Disposition

appeal dismissed

Orders

  • The appeal is dismissed with costs to the respondent.
  • The decision of the Environment and Land Court made on 11th March, 2014 is affirmed.