[2018] KEHC 1470 (KLR)

[2018] KEHC 1470 (KLR)

The court found that the plaintiffs had established a prima facie case for the grant of a mareva (freezing) injunction. The evidence indicated that the boundaries between the Zakhem entities were blurred, and the financing provided by the plaintiffs was used for the pipeline contract awarded to Zakhem Cyprus. The...

Source-derived case information.

Citation
[2018] KEHC 1470 (KLR)
Parties
Plaintiff: Ecobank Nigeria Limited; Plaintiff: Ecobank Kenya Limited; Defendant: Zakhem International Construction Nigeria Limited; Defendant: Zakhem Construction Nigeria Limited; Defendant: Zakhem International Construction Cyprus Limited; Defendant: Zakhem Construction Kenya Limited; Defendant: Kenya Pipeline Company Limited
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Case 292 of 2018
Procedural Posture
Civil Case / Ruling on Interlocutory Applications (injunctions and Striking Out)
Outcome
Plaintiffs' application for mareva and restraining injunctions granted in part; applications by Zakhem Kenya and Kenya Pipeline to be struck out dismissed.
Judges
MM Kasango
Legal Topics
Mareva Injunction, Assignment of Contractual Proceeds, Corporate Separateness, Joinder of Parties, Interlocutory Injunctions
Source Language
en
Commercial and Corporate Civil Procedure Mareva Injunction Assignment of Contractual Proceeds Corporate Separateness Joinder of Parties Interlocutory Injunctions

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 4 Party arguments 2 Amounts and remedies 8
Sign in to unlock

Parties

Ecobank Nigeria Limited

Plaintiff

Ecobank Kenya Limited

Plaintiff

Zakhem International Construction Nigeria Limited

Defendant

Zakhem Construction Nigeria Limited

Defendant

Zakhem International Construction Cyprus Limited

Defendant

Zakhem Construction Kenya Limited

Defendant

Kenya Pipeline Company Limited

Defendant

Procedural Posture

Civil Case / Ruling on Interlocutory Applications (injunctions and Striking Out)

  1. 1 Whether the plaintiffs have established a prima facie case for the grant of a mareva (freezing) injunction against the defendants.
  2. 2 Whether the plaintiffs are entitled to a mandatory injunction compelling payment of contract proceeds.
  3. 3 Whether the 5th defendant (Kenya Pipeline Company Limited) should be struck out from the suit.

Ratio Decidendi

The court found that the plaintiffs had established a prima facie case for the grant of a mareva (freezing) injunction. The evidence indicated that the boundaries between the Zakhem entities were blurred, and the financing provided by the plaintiffs was used for the pipeline contract awarded to Zakhem Cyprus. The plaintiffs demonstrated a risk of irreparable harm if the injunction was not granted, as there was no clear evidence of Zakhem Nigeria's assets in Kenya and a real risk of dissipation. The court declined to grant a mandatory injunction compelling payment of proceeds, as this would amount to determining the substantive suit at the interlocutory stage. The applications by Zakhem...

Court Disposition

Plaintiffs' application for mareva and restraining injunctions granted in part; applications by Zakhem Kenya and Kenya Pipeline to be struck out dismissed.

Orders

  • A temporary mareva (freezing) injunction is granted restraining the 1st, 2nd, 3rd, and 4th defendants from disposing, assigning, transferring, or otherwise dealing with their bank accounts or assets in Kenya.
  • A temporary injunction is granted restraining the defendants from paying, transferring, or disposing of any proceeds due under the Agreement dated 1st July 2014 between the 3rd and 5th defendants other than to the plaintiffs.