[2015] KEHC 3007 (KLR)

[2015] KEHC 3007 (KLR)

The court found that the applicant's grievance was not with the creation of the wayleave itself, but with the adequacy of compensation offered. The respondent had complied with statutory and constitutional requirements by notifying the applicant and offering compensation based on a registered valuer's assessment....

Source-derived case information.

Citation
[2015] KEHC 3007 (KLR)
Parties
Applicant: Edward Saya Malovi Juma; Respondent: Kenya Electricity Transmission Co. Ltd
Court
High Court
Court Station
High Court at Kakamega
Jurisdiction
Kenya
Case Number
Environment & Land Case 654 of 2014
Procedural Posture
Interlocutory Injunction Application / Ruling on Application for Temporary Injunction Pending Hearing of Suit
Outcome
application dismissed with costs
Legal Topics
Wayleave Acquisition, Compensation for Land, Injunctive Relief, Public Interest Vs Private Rights
Source Language
en
Land and Property Civil Procedure Wayleave Acquisition Compensation for Land Injunctive Relief Public Interest Vs Private Rights

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 10 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

Edward Saya Malovi Juma

Applicant

Kenya Electricity Transmission Co. Ltd

Respondent

Procedural Posture

Interlocutory Injunction Application / Ruling on Application for Temporary Injunction Pending Hearing of Suit

  1. 1 Whether the applicant is entitled to a temporary injunction restraining the respondent from interfering with his land pending the hearing of the suit.
  2. 2 Whether the compensation offered for the wayleave is adequate and in accordance with the law.
  3. 3 Whether the applicant will suffer irreparable harm if the injunction is not granted.

Ratio Decidendi

The court found that the applicant's grievance was not with the creation of the wayleave itself, but with the adequacy of compensation offered. The respondent had complied with statutory and constitutional requirements by notifying the applicant and offering compensation based on a registered valuer's assessment. The applicant failed to demonstrate a prima facie case or irreparable harm, as any loss could be adequately compensated by damages. The law provides a mechanism for resolving disputes over compensation amounts through court determination under Section 148 of the Land Act. The balance of convenience favoured the respondent and the public interest, as the project was of national...

Court Disposition

application dismissed with costs

Orders

  • The application dated 18/12/2014 is declined and dismissed with costs.