[2020] KEHC 4515 (KLR)

[2020] KEHC 4515 (KLR)

The court found that a valid contract existed between the defendant and the 2nd third party for the supply and installation of specialized locks, as confirmed by forensic evidence and the conduct of the parties. However, the defendant failed to comply with the contractual procedure for assessment and certification...

Source-derived case information.

Citation
[2020] KEHC 4515 (KLR)
Parties
Plaintiff: Edwin Ng’ong’a K’ogwe; Defendant: Pinkertons Kenya Limited; Respondent: Arprim Consultants; Respondent: China Wu Yi Company Limited
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Case 564 of 2014
Procedural Posture
Civil Suit / Judgment After Mediated Settlement Between Plaintiff and Defendant; Determination of Third Party Claims
Outcome
Partial judgment; mediated settlement between plaintiff and defendant adopted; defendant's claim against third parties to be assessed per contract.
Judges
GL Nzioka
Legal Topics
Breach of Contract, Sub Contracts, Construction Disputes, Third Party Procedure, Contractual Liability, Remedies for Breach
Source Language
en
Commercial and Corporate Civil Procedure Breach of Contract Sub Contracts Construction Disputes Third Party Procedure Contractual Liability Remedies for Breach

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 12 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Edwin Ng’ong’a K’ogwe

Plaintiff

Pinkertons Kenya Limited

Defendant

Arprim Consultants

Respondent

China Wu Yi Company Limited

Respondent

Procedural Posture

Civil Suit / Judgment After Mediated Settlement Between Plaintiff and Defendant; Determination of Third Party Claims

  1. 1 Whether there was a valid contract between the defendant and the third parties, and if so, whether it was breached and by whom.
  2. 2 Whether the defendant is entitled to payment or indemnity from the third parties for works performed under the contract.
  3. 3 Whether the 1st third party is liable to the defendant for any relief or remedy.

Ratio Decidendi

The court found that a valid contract existed between the defendant and the 2nd third party for the supply and installation of specialized locks, as confirmed by forensic evidence and the conduct of the parties. However, the defendant failed to comply with the contractual procedure for assessment and certification of works as required by clause 23 of the contract. The court held that the 1st third party was not privy to the contract and bore no liability. The 2nd third party, as main contractor, was responsible for verifying the defendant's claim through the quantity surveyor and architect. In the absence of a certified amount due, the court could not make a final determination on the...

Court Disposition

Partial judgment; mediated settlement between plaintiff and defendant adopted; defendant's claim against third parties to be assessed per contract.

Orders

  • The mediated consent between plaintiff and defendant for Kshs. 19,400,000 plus interest is adopted as judgment.
  • The defendant shall submit its claim to the 2nd third party for assessment and certification by the quantity surveyor and architect within 21 days.