[2015] KEHC 8365 (KLR)

[2015] KEHC 8365 (KLR)

The court found that the Plaintiff/Applicant failed to establish a prima facie case with a probability of success. The evidence showed that the Plaintiff was responsible for procuring and taking delivery of the machinery under the Hire Purchase Agreements, and the Defendants had fulfilled their obligations by...

Source-derived case information.

Citation
[2015] KEHC 8365 (KLR)
Parties
Plaintiff: Elex Products East Africa Limited; Defendant: Business Partners International Kenya SME Fund; Defendant: Business Partners International Limited
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Suit 610 of 2014
Procedural Posture
Civil Suit / Ruling on Interlocutory Injunction Application
Outcome
application dismissed with costs
Judges
OA Sewe
Legal Topics
Interlocutory Injunctions, Joint Venture Disputes, Hire Purchase Agreements, Equitable Relief, Breach of Contract
Source Language
en
Commercial and Corporate Civil Procedure Interlocutory Injunctions Joint Venture Disputes Hire Purchase Agreements Equitable Relief Breach of Contract

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 7 Party arguments 2 Amounts and remedies 7
Sign in to unlock

Parties

Elex Products East Africa Limited

Plaintiff

Business Partners International Kenya SME Fund

Defendant

Business Partners International Limited

Defendant

Procedural Posture

Civil Suit / Ruling on Interlocutory Injunction Application

  1. 1 Whether the Plaintiff/Applicant has established a prima facie case with a probability of success to warrant the grant of a temporary injunction.
  2. 2 Whether the Plaintiff/Applicant would suffer irreparable harm if the injunction is not granted.
  3. 3 Whether the balance of convenience lies in favour of granting the injunction.

Ratio Decidendi

The court found that the Plaintiff/Applicant failed to establish a prima facie case with a probability of success. The evidence showed that the Plaintiff was responsible for procuring and taking delivery of the machinery under the Hire Purchase Agreements, and the Defendants had fulfilled their obligations by releasing funds. The Plaintiff's claim that the Defendants were negligent in failing to pay customs duties was unsupported, as the contractual responsibility lay with the Plaintiff. Furthermore, the Plaintiff was in default of several agreements and had not performed its essential contractual obligations. The court held that equity does not assist parties in default or relieve them...

Court Disposition

application dismissed with costs

Orders

  • The Notice of Motion dated 21st January 2015 is dismissed with costs to the Defendants.