[2020] KEHC 1440 (KLR)

[2020] KEHC 1440 (KLR)

The court found that there exists an arbitration agreement between the applicant and the 1st respondent, as evidenced by the contract and the arbitration clause. The 1st respondent's assertion that the contract was revoked was unsupported by documentary evidence. The court held that the question of contract validity...

Source-derived case information.

Citation
[2020] KEHC 1440 (KLR)
Parties
Applicant: Elite Earthmovers Limited; Respondent: Machakos County Government; Respondent: Pointmark Valuers Limited
Court
High Court
Court Station
High Court at Machakos
Jurisdiction
Kenya
Case Number
Miscellaneous Application 424 of 2019
Procedural Posture
Miscellaneous Application / Ruling on Interim Measures of Protection Pending Arbitration
Outcome
Application partly allowed.
Judges
GV Odunga
Legal Topics
Arbitration Agreements, Interim Injunctions, Contractual Disputes, Public Procurement, Status Quo Orders, Performance Bonds
Source Language
en
Commercial and Corporate Civil Procedure Alternative Dispute Resolution Arbitration Agreements Interim Injunctions Contractual Disputes Public Procurement Status Quo Orders +1 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 11 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

Elite Earthmovers Limited

Applicant

Machakos County Government

Respondent

Pointmark Valuers Limited

Respondent

Procedural Posture

Miscellaneous Application / Ruling on Interim Measures of Protection Pending Arbitration

  1. 1 Whether there exists an enforceable arbitration agreement between the applicant and the 1st respondent.
  2. 2 Whether the subject matter of the arbitration is under threat and requires interim protection.
  3. 3 Whether the High Court should grant interim measures of protection pending arbitration, including restraining re-advertisement of the tender and payments to third parties.

Ratio Decidendi

The court found that there exists an arbitration agreement between the applicant and the 1st respondent, as evidenced by the contract and the arbitration clause. The 1st respondent's assertion that the contract was revoked was unsupported by documentary evidence. The court held that the question of contract validity and termination falls within the jurisdiction of the arbitral tribunal, not the court, in line with the principle of competence-competence and separability. The court further determined that the subject matter of the arbitration—the contract for the construction of Masii Stadium and related payments—was under threat due to the 1st respondent's actions in re-advertising the...

Court Disposition

Application partly allowed.

Orders

  • Order restraining the 1st Respondent from making payments to any other party other than the Applicant pending determination of the application.
  • Order permitting the Applicant to remove its material and equipment from the site (already granted on 19th November, 2019).