[2016] KEHC 8652 (KLR)

[2016] KEHC 8652 (KLR)

The court found that both parties were in breach of the arbitral award: the applicant defaulted on payment, while the respondent failed to move back to the construction site as required. Although the award did not expressly provide for consequences of the respondent's default, the court held that it would be...

Source-derived case information.

Citation
[2016] KEHC 8652 (KLR)
Parties
Respondent: Elsek & Elsek Construction Company Limited; Applicant: Presbyterian University of East Africa Registered Trustees
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Miscellaneous Application 356 of 2015
Procedural Posture
Miscellaneous Application / Ruling on Application for Stay of Execution and Restitution of Attached Property
Outcome
Application partially allowed; payment schedule varied; attached vehicles to be restituted; each party to bear own costs.
Legal Topics
Arbitral Awards Enforcement, Consent Awards, Breach of Settlement Terms, Execution of Decrees
Source Language
en
Commercial and Corporate Alternative Dispute Resolution Arbitral Awards Enforcement Consent Awards Breach of Settlement Terms Execution of Decrees

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 2 Party arguments 2 Amounts and remedies 5
Sign in to unlock

Parties

Elsek & Elsek Construction Company Limited

Respondent

Presbyterian University of East Africa Registered Trustees

Applicant

Procedural Posture

Miscellaneous Application / Ruling on Application for Stay of Execution and Restitution of Attached Property

  1. 1 Whether the execution process initiated by the respondent was premature in light of the arbitral award terms.
  2. 2 Whether the respondent was in breach of the arbitral award by failing to move back to the construction site after the first installment was paid.
  3. 3 Whether the applicant's default in payment was excusable due to the respondent's alleged breach.

Ratio Decidendi

The court found that both parties were in breach of the arbitral award: the applicant defaulted on payment, while the respondent failed to move back to the construction site as required. Although the award did not expressly provide for consequences of the respondent's default, the court held that it would be inequitable to allow the respondent to benefit from its own breach, which likely contributed to the applicant's inability to pay. The court therefore ordered a mutual variation of the payment schedule, pegging future payments to the respondent's actual return to the site and completion of construction. The attached vehicles were to be released to the applicant to facilitate its...

Court Disposition

Application partially allowed; payment schedule varied; attached vehicles to be restituted; each party to bear own costs.

Orders

  • The respondent shall move onto the site of ELSEK II and complete construction as agreed.
  • The payment schedule is varied such that the next installment is due three months after the respondent moves onto the site.