[2020] KEHC 9328 (KLR)

[2020] KEHC 9328 (KLR)

The court found that the delays in the project were primarily attributable to Eswari Electricals (Pvt) Limited and KENGEN, due to their failure to provide necessary drawings, materials, and effective communication, as evidenced by uncontested correspondence and third-party (KENGEN) documentation. Empower...

Source-derived case information.

Citation
[2020] KEHC 9328 (KLR)
Parties
Plaintiff: Empower Installations Limited; Defendant: Eswari Electricals (Pvt) Limited
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Case 106 of 2013
Procedural Posture
Civil Case / Judgment
Outcome
Judgment for the plaintiff; counterclaim and set-off dismissed.
Judges
DAS Majanja
Legal Topics
Breach of Contract, Subcontractor Liability, Quantum Meruit, Delay Damages, Set Off, Counterclaim
Source Language
en
Commercial and Corporate Civil Procedure Breach of Contract Subcontractor Liability Quantum Meruit Delay Damages Set Off Counterclaim

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Party arguments 2 Amounts and remedies 5
Sign in to unlock

Parties

Empower Installations Limited

Plaintiff

Eswari Electricals (Pvt) Limited

Defendant

Procedural Posture

Civil Case / Judgment

  1. 1 Whether Empower Installations Limited was responsible for the delay in completion of the project under the Sub-contract.
  2. 2 Whether Eswari Electricals (Pvt) Limited is entitled to damages for delay and other losses claimed in the counterclaim and set-off.
  3. 3 Whether Empower Installations Limited is entitled to payment for the value of work done under the Sub-contract.

Ratio Decidendi

The court found that the delays in the project were primarily attributable to Eswari Electricals (Pvt) Limited and KENGEN, due to their failure to provide necessary drawings, materials, and effective communication, as evidenced by uncontested correspondence and third-party (KENGEN) documentation. Empower Installations Limited was not responsible for the delays and had repeatedly raised concerns about the lack of support and payment. The court held that Eswari failed to discharge its burden of proof regarding Empower's liability for delay and was therefore not entitled to damages or set-off for delay or administrative expenses. The court further held that Empower was entitled to payment...

Court Disposition

Judgment for the plaintiff; counterclaim and set-off dismissed.

Orders

  • Judgment entered for the plaintiff against the defendant for Kshs. 20,536,637.00.
  • Interest on the judgment sum at court rates from 5th August 2016 until payment in full.