[2024] KEELC 413 (KLR)

[2024] KEELC 413 (KLR)

The court found that Bhupinder Singh Dogra, not being an authorized director of Enacta Limited, improperly instituted the suit in the company's name. The only directors per official records were the 1st and 2nd Defendants, who neither authorized nor participated in the suit's institution. The Plaintiff failed to...

Source-derived case information.

Citation
[2024] KEELC 413 (KLR)
Parties
Plaintiff: Enacta Limited; 1st Defendant: Martin Mureithi Ngari; 2nd Defendant: Beatrice Wacera Ngari; 3rd Defendant: Lahari Jethanand Manghnani T/a Sachedeva & Company Advocate; 4th Defendant: Land Registrar Mombasa County; 5th Defendant: Kenya Commercial Bank; 6th Defendant: Attorney General
Court
Environment and Land Court
Court Station
Environment and Land Court at Mombasa
Jurisdiction
Kenya
Case Number
Environment & Land Case E228 of 2021
Procedural Posture
Environment and Land Case / Ruling on Costs and Joinder Application Post Striking Out of Suit
Outcome
Application allowed; suit marked as settled and dismissed; Bhupinder Singh Dogra to personally bear costs; 1st and 2nd Defendants exempted from costs liability.
Judges
LL Naikuni
Legal Topics
Costs Follow the Event, Lifting Corporate Veil, Joinder of Parties, Company Directorship Disputes
Source Language
en
Civil Procedure Commercial and Corporate Costs Follow the Event Lifting Corporate Veil Joinder of Parties Company Directorship Disputes

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 8 Party arguments 2
Sign in to unlock

Parties

Enacta Limited

Plaintiff

Martin Mureithi Ngari

1st Defendant

Beatrice Wacera Ngari

2nd Defendant

Lahari Jethanand Manghnani T/a Sachedeva & Company Advocate

3rd Defendant

Land Registrar Mombasa County

4th Defendant

Kenya Commercial Bank

5th Defendant

Attorney General

6th Defendant

Procedural Posture

Environment and Land Case / Ruling on Costs and Joinder Application Post Striking Out of Suit

  1. 1 Whether Bhupinder Singh Dogra should be joined to the suit for purposes of costs liability.
  2. 2 Whether the 3rd Defendant is entitled to costs and against whom such costs should be awarded.
  3. 3 Whether the Plaintiff company or Bhupinder Singh Dogra should bear the costs of the struck out suit.

Ratio Decidendi

The court found that Bhupinder Singh Dogra, not being an authorized director of Enacta Limited, improperly instituted the suit in the company's name. The only directors per official records were the 1st and 2nd Defendants, who neither authorized nor participated in the suit's institution. The Plaintiff failed to comply with a prior court order to regularize its verifying affidavit, resulting in the suit being struck out. Given these facts, and applying the principle that costs follow the event, the court exercised its discretion to order that Dogra personally bear the costs of the suit and the application. The court expressly exempted the 1st and 2nd Defendants from any costs liability,...

Court Disposition

Application allowed; suit marked as settled and dismissed; Bhupinder Singh Dogra to personally bear costs; 1st and 2nd Defendants exempted from costs liability.

Orders

  • The Notice of Motion application dated 15th March, 2023 by the 3rd Defendant/Applicant is allowed with costs.
  • The suit by the Plaintiff stands automatically dismissed and is marked as settled.