[2023] KEHC 1059 (KLR)

[2023] KEHC 1059 (KLR)

The court held that although the arbitrator found the Respondent responsible for project delays, the Applicant condoned and allowed multiple extensions, resulting in additional costs that were foreseeable and compensable. The arbitrator's findings on liability for security and staff maintenance expenses were based...

Source-derived case information.

Citation
[2023] KEHC 1059 (KLR)
Parties
Applicant: Energy Corporation; Respondent: Penelly Construction and Engineering Limited
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Miscellaneous Application E424 of 2022
Procedural Posture
Miscellaneous Application / Ruling on Application to Set Aside Arbitral Award
Outcome
Application dismissed with costs to the Respondent.
Judges
DAS Majanja
Legal Topics
Arbitration Awards, Public Policy Challenge, Contractual Disputes, Unjust Enrichment, Construction Contracts
Source Language
en
Commercial and Corporate Alternative Dispute Resolution Arbitration Awards Public Policy Challenge Contractual Disputes Unjust Enrichment Construction Contracts

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 7 Party arguments 2 Amounts and remedies 5
Sign in to unlock

Parties

Energy Corporation

Applicant

Penelly Construction and Engineering Limited

Respondent

Procedural Posture

Miscellaneous Application / Ruling on Application to Set Aside Arbitral Award

  1. 1 Whether the arbitral award should be set aside for being contrary to public policy under section 35(2)(b)(ii) of the Arbitration Act, 1995.
  2. 2 Whether the award amounts to unjust enrichment of the Respondent beyond the contract sum.
  3. 3 Whether the arbitrator erred in awarding costs for security and staff maintenance despite finding the Respondent responsible for delay.

Ratio Decidendi

The court held that although the arbitrator found the Respondent responsible for project delays, the Applicant condoned and allowed multiple extensions, resulting in additional costs that were foreseeable and compensable. The arbitrator's findings on liability for security and staff maintenance expenses were based on evidence and within his jurisdiction. The award was compensatory, not punitive, and did not amount to unjust enrichment. The Applicant failed to demonstrate that the award was inconsistent with the Constitution, law, national interest, or justice and morality. The court emphasized that it cannot substitute its own view for that of the arbitrator or sit as an appellate court...

Court Disposition

Application dismissed with costs to the Respondent.

Orders

  • The Applicant's Notice of Motion dated 7th June 2022 is dismissed.
  • The Respondent is awarded costs assessed at Kshs. 200,000.00.