[2014] KEHC 859 (KLR)

[2014] KEHC 859 (KLR)

The court found that while Clause 34.22 of the contract generally makes the Final Certificate conclusive, it contains exceptions, notably for defects not reasonably discoverable before issuance. The Defendant raised issues regarding a certificate of loss, interest calculations, and rectification of defects, all of...

Source-derived case information.

Citation
[2014] KEHC 859 (KLR)
Parties
Plaintiff: EPCO Builders Limited; Defendant: South Development Company Limited
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Case 188 of 2013
Procedural Posture
Civil Case / Ruling on Application for Stay and Reference to Arbitration
Outcome
Application allowed. Suit stayed and parties referred to arbitration. Costs to Defendant.
Judges
DO Ogembo
Legal Topics
Arbitration Clauses, Building Contracts, Final Certificates, Interest on Delayed Payments, Contractual Disputes, Stay of Proceedings
Source Language
en
Commercial and Corporate Civil Procedure Alternative Dispute Resolution Arbitration Clauses Building Contracts Final Certificates Interest on Delayed Payments Contractual Disputes +1 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 6 Party arguments 2 Amounts and remedies 5
Sign in to unlock

Parties

EPCO Builders Limited

Plaintiff

South Development Company Limited

Defendant

Procedural Posture

Civil Case / Ruling on Application for Stay and Reference to Arbitration

  1. 1 Whether Clause 34.22 of the contract renders the final certificate conclusive and unchallengeable in this dispute.
  2. 2 Whether there exists a dispute between the parties that should be referred to arbitration under Section 6 of the Arbitration Act.
  3. 3 Whether the Defendant's application for stay of proceedings and reference to arbitration is merited.

Ratio Decidendi

The court found that while Clause 34.22 of the contract generally makes the Final Certificate conclusive, it contains exceptions, notably for defects not reasonably discoverable before issuance. The Defendant raised issues regarding a certificate of loss, interest calculations, and rectification of defects, all of which the Plaintiff disputed or failed to address. The court determined that these matters constitute genuine disputes within the meaning of Section 6 of the Arbitration Act and fall within the scope of the arbitration clause. The Plaintiff's argument that the Final Certificate is conclusive was rejected to the extent that the exceptions in Clause 34.22.2 apply. The court held...

Court Disposition

Application allowed. Suit stayed and parties referred to arbitration. Costs to Defendant.

Orders

  • The suit herein is stayed pending the hearing and determination of the dispute through arbitration.
  • The dispute between the parties is referred to a sole arbitrator in accordance with the terms of the arbitration agreement in the Building Works Contract.