[2014] KEHC 4941 (KLR)

[2014] KEHC 4941 (KLR)

The plaintiff failed to pay the full purchase price within the period stipulated in the sale agreement, thereby breaching a fundamental term that made time of the essence. The contract expressly allowed the vendor to resell the property and refund the sums paid less a penalty in the event of default. The plaintiff's...

Source-derived case information.

Citation
[2014] KEHC 4941 (KLR)
Parties
Plaintiff: Ernest Njagi Muthara; Defendant: Nderitu Wachira (Receiver & Manager, Bulleys Tanneries Ltd); Defendant: Evanson M. Karanja
Court
High Court
Court Station
High Court at Nairobi (Milimani Law Courts)
Jurisdiction
Kenya
Case Number
Environment & Land Case 482 of 2012
Procedural Posture
Notice of Motion / Ruling on Interlocutory Application for Injunction and Specific Performance
Outcome
application dismissed with costs to the defendants/respondents
Legal Topics
Specific Performance, Injunctive Relief, Breach of Contract, Adverse Possession, Sale of Land, Equitable Remedies
Source Language
en
Land and Property Civil Procedure Specific Performance Injunctive Relief Breach of Contract Adverse Possession Sale of Land Equitable Remedies

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 10 Party arguments 2 Amounts and remedies 5
Sign in to unlock

Parties

Ernest Njagi Muthara

Plaintiff

Nderitu Wachira (Receiver & Manager, Bulleys Tanneries Ltd)

Defendant

Evanson M. Karanja

Defendant

Procedural Posture

Notice of Motion / Ruling on Interlocutory Application for Injunction and Specific Performance

  1. 1 Whether the plaintiff is entitled to a permanent injunction restraining the defendants from dealing with the suit property.
  2. 2 Whether the plaintiff is entitled to an order of specific performance compelling transfer of the suit property.
  3. 3 Whether the plaintiff has established a prima facie case with a probability of success to warrant injunctive relief.

Ratio Decidendi

The plaintiff failed to pay the full purchase price within the period stipulated in the sale agreement, thereby breaching a fundamental term that made time of the essence. The contract expressly allowed the vendor to resell the property and refund the sums paid less a penalty in the event of default. The plaintiff's delay of over a decade in seeking to complete the transaction was unreasonable and not excusable by the vendor's subsequent receivership, which occurred years after the breach. The property was lawfully transferred to a third party, and the plaintiff's payment of rates or alleged possession did not confer proprietary rights. As the event sought to be restrained had already...

Court Disposition

application dismissed with costs to the defendants/respondents

Orders

  • The Notice of Motion dated 19th April, 2013 is dismissed in its entirety.
  • Costs of the application are awarded to the defendants/respondents.