[2001] KEHC 629 (KLR)

[2001] KEHC 629 (KLR)

The court found that, although the architect had certified the amount claimed by the plaintiff as due, there remained unresolved issues regarding variations and measurements that could affect the final sum payable. These issues were present before the suit was filed and were detailed in the Project Report and...

Source-derived case information.

Citation
[2001] KEHC 629 (KLR)
Parties
Plaintiff: Ernie Cambell & Company Ltd.; Defendant: Githunguri Dairy Plant Company Ltd.
Court
High Court
Court Station
High Court at Nairobi (Milimani Law Courts)
Jurisdiction
Kenya
Case Number
? 1562 of ??
Procedural Posture
Civil Case / Ruling on Application for Reference to Arbitration
Outcome
Application allowed; dispute referred to arbitration.
Legal Topics
Arbitration Agreements, Building Contracts, Certification of Payments, Dispute Resolution, Variation of Contracts
Source Language
en
Commercial and Corporate Civil Procedure Arbitration Agreements Building Contracts Certification of Payments Dispute Resolution Variation of Contracts

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 4 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Ernie Cambell & Company Ltd.

Plaintiff

Githunguri Dairy Plant Company Ltd.

Defendant

Procedural Posture

Civil Case / Ruling on Application for Reference to Arbitration

  1. 1 Whether the dispute between the parties falls within the scope of the arbitration agreement and should be referred to arbitration.
  2. 2 Whether there exists a genuine dispute regarding the amount certified as due under the building contract.
  3. 3 Whether the existence of certified payment negates the presence of a dispute suitable for arbitration.

Ratio Decidendi

The court found that, although the architect had certified the amount claimed by the plaintiff as due, there remained unresolved issues regarding variations and measurements that could affect the final sum payable. These issues were present before the suit was filed and were detailed in the Project Report and affidavits. The court held that such disputes fall squarely within the arbitration clause of the contract, which covers matters left to the architect's discretion, including measurement and valuation. The existence of these disputes distinguishes the case from authorities where the debt was admitted and no dispute existed. Accordingly, the court determined that the dispute should be...

Court Disposition

Application allowed; dispute referred to arbitration.

Orders

  • The dispute herein is referred to arbitration in accordance with the arbitration agreement.
  • Costs of this application awarded to the applicant.