[2015] KEHC 8291 (KLR)

[2015] KEHC 8291 (KLR)

The court held that the continued detention of the plaintiff's drilling rig and accessories by the defendant was prejudicial to both parties and not justified as an interim measure pending arbitration. The court found that interim measures of protection under section 7 of the Arbitration Act are not limited to...

Source-derived case information.

Citation
[2015] KEHC 8291 (KLR)
Parties
Plaintiff: Euro Water Services Limited; Defendant: Peter Gatune
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Suit 208 of 2015
Procedural Posture
Civil Suit / Interlocutory Application for Interim Relief Pending Arbitration
Outcome
Application allowed in part; interim release of equipment ordered pending arbitration.
Legal Topics
Arbitration Referral, Interim Measures, Contractual Obligations, Equipment Detention
Source Language
en
Commercial and Corporate Alternative Dispute Resolution Arbitration Referral Interim Measures Contractual Obligations Equipment Detention

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 7 Party arguments 2
Sign in to unlock

Parties

Euro Water Services Limited

Plaintiff

Peter Gatune

Defendant

Procedural Posture

Civil Suit / Interlocutory Application for Interim Relief Pending Arbitration

  1. 1 Whether the dispute should be referred to arbitration as per the contract.
  2. 2 Whether the plaintiff is entitled to interim release of its drilling rig and accessories pending arbitration.
  3. 3 Whether continued detention of the plaintiff's equipment by the defendant is justified.

Ratio Decidendi

The court held that the continued detention of the plaintiff's drilling rig and accessories by the defendant was prejudicial to both parties and not justified as an interim measure pending arbitration. The court found that interim measures of protection under section 7 of the Arbitration Act are not limited to preservation but extend to any order necessary to prevent prejudice to the subject matter of the dispute. The court emphasized that it would not make any determination on the substantive rights of the parties, which are reserved for the arbitrator. However, to avoid further financial loss to the plaintiff and potential prejudice to both parties, the court ordered the release of the...

Court Disposition

Application allowed in part; interim release of equipment ordered pending arbitration.

Orders

  • The defendant shall release to the plaintiff the Drilling Rig, Drilling pipes, and accessories held by the defendant.
  • The plaintiff must, within 7 days, provide a written undertaking to the defendant to settle any compensation the plaintiff may be held liable for upon determination of the arbitration.