[2024] KEELC 5673 (KLR)

[2024] KEELC 5673 (KLR)

The court held that the preliminary objection raised by the Defendant was not sustainable because it required evidentiary proof to ascertain whether the Energy Act 2019 applied retrospectively to a suit filed before its enactment. This need for factual determination disqualified the objection as a pure point of law...

Source-derived case information.

Citation
[2024] KEELC 5673 (KLR)
Parties
Plaintiff: Aziz Omar Fadhil; Defendant: Kenya Power & Lighting Company Limited
Court
Environment and Land Court
Court Station
Environment and Land Court at Malindi
Jurisdiction
Kenya
Case Number
Environment & Land Case 49 of 2017
Procedural Posture
Preliminary Objection / Ruling on Preliminary Objection
Outcome
preliminary objection struck out with costs to the plaintiff
Judges
FM Njoroge
Legal Topics
Preliminary Objection, Jurisdiction, Retrospective Application of Statute, Wayleave Disputes
Source Language
en
Civil Procedure Land and Property Preliminary Objection Jurisdiction Retrospective Application of Statute Wayleave Disputes

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 6 Party arguments 2
Sign in to unlock

Parties

Aziz Omar Fadhil

Plaintiff

Kenya Power & Lighting Company Limited

Defendant

Procedural Posture

Preliminary Objection / Ruling on Preliminary Objection

  1. 1 Whether the court has jurisdiction to hear the suit in light of the Energy Act 2019 and related regulations.
  2. 2 Whether the preliminary objection raises a pure point of law suitable for determination at this stage.
  3. 3 Whether the Energy Act 2019 applies retrospectively to a suit filed before its enactment.

Ratio Decidendi

The court held that the preliminary objection raised by the Defendant was not sustainable because it required evidentiary proof to ascertain whether the Energy Act 2019 applied retrospectively to a suit filed before its enactment. This need for factual determination disqualified the objection as a pure point of law suitable for a preliminary objection. Furthermore, the Defendant's own defence admitted the court's jurisdiction and the suit was already partly heard. Therefore, the preliminary objection was struck out with costs to the Plaintiff.

Court Disposition

preliminary objection struck out with costs to the plaintiff

Orders

  • The preliminary objection dated 13th March 2024 is struck out with costs to the Plaintiff.
  • The suit shall be mentioned on 30th September 2024 for the issuance of a hearing date.