[2023] KEHC 27541 (KLR)

[2023] KEHC 27541 (KLR)

The court found that a valid contract existed between the parties, and the Plaintiff had completed the contracted works as evidenced by certificates of completion and making good defects. The Defendant failed to pay the full contractual sum, with a balance of Kshs. 12,554,980.25 remaining unpaid. The Defendant did...

Source-derived case information.

Citation
[2023] KEHC 27541 (KLR)
Parties
Plaintiff: Fahari Building and Civil Engineering Limited; Defendant: Attorney General (on behalf of the Ministry of Interior and Coordination of National Government and the Director of Kenya School of Government)
Court
High Court
Court Station
High Court at Mombasa
Jurisdiction
Kenya
Case Number
Commercial Case 05 of 2020
Procedural Posture
Commercial Case / Judgment
Outcome
Judgment for the Plaintiff.
Judges
F Wangari
Legal Topics
Breach of Contract, Construction Contracts, Liquidated Damages, Interest Awards
Source Language
en
Commercial and Corporate Civil Procedure Breach of Contract Construction Contracts Liquidated Damages Interest Awards

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 17 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Fahari Building and Civil Engineering Limited

Plaintiff

Attorney General (on behalf of the Ministry of Interior and Coordination of National Government and the Director of Kenya School of Government)

Defendant

Procedural Posture

Commercial Case / Judgment

  1. 1 Whether the Defendant breached the contract dated 5th June 2008 by failing to pay the Plaintiff the outstanding contractual sum.
  2. 2 Whether the Plaintiff is entitled to the claimed sum, interest, and costs.

Ratio Decidendi

The court found that a valid contract existed between the parties, and the Plaintiff had completed the contracted works as evidenced by certificates of completion and making good defects. The Defendant failed to pay the full contractual sum, with a balance of Kshs. 12,554,980.25 remaining unpaid. The Defendant did not produce any evidence to rebut the Plaintiff's claim or to justify withholding the retention amount. The court held that partial payment is an admission of debt and that the Defendant, having ratified completion, could not later dispute payment without a genuine counterclaim or evidence of defects. The Plaintiff proved its case on a balance of probabilities, entitling it to...

Court Disposition

Judgment for the Plaintiff.

Orders

  • The Defendant shall pay Kshs. 12,554,980.25 to the Plaintiff being the outstanding balance under contract.
  • The amount shall attract interest at court rates from the date of filing the suit.