[2023] KEHC 19904 (KLR)

[2023] KEHC 19904 (KLR)

The court found that the defendant breached the contract by supplying goods that were not of merchantable quality, contrary to the Sale of Goods Act and Consumer Protection Act. While the plaintiff was entitled to damages for direct losses proven and foreseeable, claims for loss of goodwill and speculative project...

Source-derived case information.

Citation
[2023] KEHC 19904 (KLR)
Parties
Plaintiff: Fairdeal UPVC Aluminium & Glass Limited; Defendant: ASE Europe N.V
Court
High Court
Court Station
High Court at Mombasa
Jurisdiction
Kenya
Case Number
Civil Cause 85 of 2016
Procedural Posture
Civil Cause / Judgment After Formal Proof
Outcome
Judgment for the plaintiff in part; special and punitive damages awarded; other claims dismissed.
Judges
DKN Magare
Legal Topics
Breach of Contract, Merchantable Quality, Special Damages, Consumer Protection, Remoteness of Damage
Source Language
en
Commercial and Corporate Civil Procedure Breach of Contract Merchantable Quality Special Damages Consumer Protection Remoteness of Damage

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 15 Party arguments 2 Amounts and remedies 4
Sign in to unlock

Parties

Fairdeal UPVC Aluminium & Glass Limited

Plaintiff

ASE Europe N.V

Defendant

Procedural Posture

Civil Cause / Judgment After Formal Proof

  1. 1 Whether there was a breach of contract by the defendant supplying unmerchantable goods.
  2. 2 Whether special damages are payable and to what extent.
  3. 3 Whether general damages or damages for loss of goodwill are recoverable for breach of contract.

Ratio Decidendi

The court found that the defendant breached the contract by supplying goods that were not of merchantable quality, contrary to the Sale of Goods Act and Consumer Protection Act. While the plaintiff was entitled to damages for direct losses proven and foreseeable, claims for loss of goodwill and speculative project losses were dismissed for lack of proof and remoteness. The court awarded special damages only for actual losses under the Forestscape contract, man hours, transportation, and storage, as these were specifically pleaded and proved. Punitive damages were also awarded under the Consumer Protection Act due to the defendant's conduct. The claim for loss of a contract with Landmark...

Court Disposition

Judgment for the plaintiff in part; special and punitive damages awarded; other claims dismissed.

Orders

  • Judgment entered for the plaintiff for Kshs 6,686,000 as special damages.
  • Punitive damages of Kshs 6,000,000 awarded under the Consumer Protection Act.