[2019] KEHC 6866 (KLR)

[2019] KEHC 6866 (KLR)

The court found that the appellant was in breach of the agreement by failing to deliver the logbook to the respondent as required. The evidence showed that the appellant had good title and was expected to pass the logbook to the buyer, and the claim that the logbook was misplaced was considered an afterthought. The...

Source-derived case information.

Citation
[2019] KEHC 6866 (KLR)
Parties
Appellant: Farm Engineering Industries; Respondent: Sunipu Limited; Respondent: Barclays Bank of Kenya Ltd
Court
High Court
Court Station
High Court at Bungoma
Jurisdiction
Kenya
Case Number
Civil Appeal 85 of 2014
Procedural Posture
Civil Appeal / Judgment
Outcome
Appeal partially allowed; damages reduced.
Legal Topics
Breach of Contract, Damages Assessment, Sale of Goods, Contractual Obligations
Source Language
en
Commercial and Corporate Civil Procedure Breach of Contract Damages Assessment Sale of Goods Contractual Obligations

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 1 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Farm Engineering Industries

Appellant

Sunipu Limited

Respondent

Barclays Bank of Kenya Ltd

Respondent

Procedural Posture

Civil Appeal / Judgment

  1. 1 Whether the appellant was liable to deliver the logbook of KAH 806T to the respondent for registration in the respondent's name.
  2. 2 Whether the trial court properly assessed damages to be paid by the appellant to the respondent for breach of contract.

Ratio Decidendi

The court found that the appellant was in breach of the agreement by failing to deliver the logbook to the respondent as required. The evidence showed that the appellant had good title and was expected to pass the logbook to the buyer, and the claim that the logbook was misplaced was considered an afterthought. The court held that Barclays Bank was not liable as it only acted as a financier and was not a party to the sale agreement. On damages, the court determined that the respondent suffered only from the delay in receiving the logbook, not from loss of use of the loader, and that the award of Kshs.500,000 was excessive in the absence of proof of financial loss. The damages were...

Court Disposition

Appeal partially allowed; damages reduced.

Orders

  • The appellant is found liable for breach of contract for failing to deliver the logbook to the respondent.
  • Barclays Bank of Kenya Ltd is not liable for breach of contract.