[2024] KEELC 7432 (KLR)

[2024] KEELC 7432 (KLR)

The court found that the consent judgment entered on 24th September 2019 remains valid and binding, as there was no sufficient ground to set it aside. The defendant's objections based on the plaintiff's alleged foreign directorship and the constitutional bar on foreigners holding freehold land were rejected, as the...

Source-derived case information.

Citation
[2024] KEELC 7432 (KLR)
Parties
Plaintiff: Fenysan Construction Ltd; Defendant: Joseph Kasena Yeri
Court
Environment and Land Court
Court Station
Environment and Land Court at Malindi
Jurisdiction
Kenya
Case Number
Environment & Land Case 179 of 2016
Procedural Posture
Environment and Land Case / Ruling on Enforcement Application Post Judgment
Outcome
Application allowed; enforcement orders granted as prayed.
Judges
EK Makori
Legal Topics
Consent Judgment Enforcement, Transfer of Land, Foreign Ownership of Land, Execution of Decree
Source Language
en
Land and Property Civil Procedure Consent Judgment Enforcement Transfer of Land Foreign Ownership of Land Execution of Decree

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 9 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Fenysan Construction Ltd

Plaintiff

Joseph Kasena Yeri

Defendant

Procedural Posture

Environment and Land Case / Ruling on Enforcement Application Post Judgment

  1. 1 Whether the Deputy Registrar should be empowered to execute transfer documents for the suit property due to the defendant's refusal to comply with the consent judgment.
  2. 2 Whether the defendant's objections based on the plaintiff's foreign directorship and alleged legal incapacity to hold freehold land in Kenya are valid grounds to resist enforcement.
  3. 3 Who should bear the costs of the application.

Ratio Decidendi

The court found that the consent judgment entered on 24th September 2019 remains valid and binding, as there was no sufficient ground to set it aside. The defendant's objections based on the plaintiff's alleged foreign directorship and the constitutional bar on foreigners holding freehold land were rejected, as the law merely converts any such interest to a 99-year leasehold rather than rendering it void. The defendant's persistent refusal to execute the necessary transfer documents was deemed a deliberate attempt to frustrate the enforcement of the decree. The court held that it has jurisdiction to direct the Deputy Registrar to execute all requisite documents to effectuate the transfer...

Court Disposition

Application allowed; enforcement orders granted as prayed.

Orders

  • Within 15 days, the defendant/respondent shall hand over all necessary transfer documents to the plaintiff/applicant for registration of 2.8 hectares (7 acres) hived off from Ngomeni Squatter Settlement Scheme/1407.
  • If the defendant/respondent fails to comply, the Deputy Registrar is authorized to sign and execute all subdivision, land control board consent, transfer, and registration documents to enable registration of the plaintiff/applicant as owner of the said parcel.