[2014] KEELC 99 (KLR)

[2014] KEELC 99 (KLR)

The court found that the Defendant, Kenya Power & Lighting Limited, laid electric supply lines and erected poles across sixteen sub-plots of the Plaintiff's land without the Plaintiff's consent, contrary to Sections 46 and 47 of the Energy Act. The Defendant's reliance on approval from the Municipal Council of...

Source-derived case information.

Citation
[2014] KEELC 99 (KLR)
Parties
Plaintiff: Fleetwood Enterprises Limited; Defendant: Kenya Power & Lighting Limited
Court
Environment and Land Court
Court Station
Environment and Land Court at Malindi
Jurisdiction
Kenya
Case Number
Environment & Land Case 5 of 2010
Procedural Posture
Civil Case / Judgment
Outcome
Judgment for the Plaintiff.
Judges
OA Angote
Legal Topics
Trespass to Land, Compulsory Acquisition, Injunctions, Damages for Trespass
Source Language
en
Land and Property Tort Law Trespass to Land Compulsory Acquisition Injunctions Damages for Trespass

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 3 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Fleetwood Enterprises Limited

Plaintiff

Kenya Power & Lighting Limited

Defendant

Procedural Posture

Civil Case / Judgment

  1. 1 Whether the Defendant trespassed on the Plaintiff's land by erecting electric poles and laying supply lines without consent.
  2. 2 Whether the Defendant obtained the necessary approvals and wayleave consents for the works on the suit property.
  3. 3 Whether the Plaintiff is entitled to mandatory and permanent injunctions and damages for trespass.

Ratio Decidendi

The court found that the Defendant, Kenya Power & Lighting Limited, laid electric supply lines and erected poles across sixteen sub-plots of the Plaintiff's land without the Plaintiff's consent, contrary to Sections 46 and 47 of the Energy Act. The Defendant's reliance on approval from the Municipal Council of Malindi was misplaced, as the sketch plan used clearly showed the power line traversing private property, not a public road. The Defendant failed to verify the status of the land with the Department of Surveys or obtain the Plaintiff's consent, despite being aware of the private ownership. The Defendant also failed to join the Municipal Council as a third party for indemnity. The...

Court Disposition

Judgment for the Plaintiff.

Orders

  • A declaration that the Defendant has trespassed and continues to trespass on the specified sixteen sub-plots.
  • A mandatory injunction compelling the Defendant to immediately remove the illegal supply lines from the affected parcels.