[2010] KEHC 1775 (KLR)

[2010] KEHC 1775 (KLR)

The court found that the disconnection of the Applicant's electricity supply was not justified, as the meter in question was installed by the Respondent's own technician and its absence from the Respondent's records was not the Applicant's fault. The Respondent failed to provide evidence of notices for alleged...

Source-derived case information.

Citation
[2010] KEHC 1775 (KLR)
Parties
Plaintiff: Francis Irungu Mwangi; Defendant: The Kenya Power & Lighting Company Limited
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Case 94 of 2010
Procedural Posture
Civil Case / Interlocutory Application (chamber Summons) for Mandatory and Prohibitory Injunction Pending Suit
Outcome
Application allowed. Mandatory injunction granted for reconnection of electricity supply pending hearing of the suit. Costs in the cause.
Legal Topics
Injunctive Relief, Electricity Supply Disputes, Contractual Obligations, Utility Services
Source Language
en
Civil Procedure Commercial and Corporate Injunctive Relief Electricity Supply Disputes Contractual Obligations Utility Services

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 4 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Francis Irungu Mwangi

Plaintiff

The Kenya Power & Lighting Company Limited

Defendant

Procedural Posture

Civil Case / Interlocutory Application (chamber Summons) for Mandatory and Prohibitory Injunction Pending Suit

  1. 1 Whether the disconnection of the Applicant's power supply was justified in the circumstances.
  2. 2 Whether the Applicant is entitled to a mandatory injunction for reconnection of electricity pending the hearing of the suit.
  3. 3 Whether the Applicant should be held liable for alleged arrears based on disputed meter readings.

Ratio Decidendi

The court found that the disconnection of the Applicant's electricity supply was not justified, as the meter in question was installed by the Respondent's own technician and its absence from the Respondent's records was not the Applicant's fault. The Respondent failed to provide evidence of notices for alleged arrears, and the demand for payment based on readings from a faulty or unregistered meter was inequitable. The court held that the Applicant had established a strong prima facie case for the grant of a mandatory injunction, and that the Respondent's conduct was unfair and high-handed. The Applicant was entitled to reconnection of power supply pending the hearing of the suit, with an...

Court Disposition

Application allowed. Mandatory injunction granted for reconnection of electricity supply pending hearing of the suit. Costs in the cause.

Orders

  • The Respondent shall forthwith reconnect the power supply to the Applicant's premises pending the hearing of the suit.
  • The parties may resolve the dispute under Rule 4 of the Electric Power (Complaints and Disputes Resolution) Rules 2006 without going to court.