The court found that a contract existed between Njenga and Bodymasters for the construction of five mini-bus bodies, with an express term that completion would occur within 45 working days of receipt of each chassis, failing which liquidated damages of Kshs 1,500 per day would be payable. Bodymasters admitted breach...

Source-derived case information.

Citation
[2018] KEHC 2817 (KLR)
Parties
Plaintiff: Francis Kigo Njenga; Defendant: Bodymasters Autotech Limited
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Case 645 of 2008
Procedural Posture
Civil Case / Judgment
Outcome
Judgment for the plaintiff.
Judges
F Tuiyott
Legal Topics
Breach of Contract, Liquidated Damages, Measure of Damages, Privity of Contract
Source Language
en
Commercial and Corporate Civil Procedure Breach of Contract Liquidated Damages Measure of Damages Privity of Contract

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 1 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Francis Kigo Njenga

Plaintiff

Bodymasters Autotech Limited

Defendant

Procedural Posture

Civil Case / Judgment

  1. 1 Was there a contract for the building of bodies between Njenga and Bodymasters?
  2. 2 Did Bodymasters breach that contract?
  3. 3 What measure of damages, if any, is Njenga entitled to?

Ratio Decidendi

The court found that a contract existed between Njenga and Bodymasters for the construction of five mini-bus bodies, with an express term that completion would occur within 45 working days of receipt of each chassis, failing which liquidated damages of Kshs 1,500 per day would be payable. Bodymasters admitted breach by failing to complete the works within the stipulated period and could not prove payment of default penalties. The court held that the plaintiff was entitled to liquidated damages for the delay, calculated at Kshs 1,500 per day for 794 days, totaling Kshs 1,191,000. The court further held that the plaintiff was entitled to recover additional costs reasonably incurred to...

Court Disposition

Judgment for the plaintiff.

Orders

  • Plaintiff awarded Kshs 1,191,000 as liquidated damages for delay, with interest at court rates from the date of judgment.
  • Plaintiff awarded Kshs 954,920 as extra costs incurred to complete the works, with interest at court rates from the date of filing suit.