[2006] KEHC 684 (KLR)

[2006] KEHC 684 (KLR)

The court found that the plaintiffs failed to establish a prima facie case with a probability of success, as the performance bond was valid until the certificate of completion and the defendant was obliged to pay upon demand by KPLC. The plaintiffs had benefited from the bond and could not challenge its validity on...

Source-derived case information.

Citation
[2006] KEHC 684 (KLR)
Parties
Plaintiff: Francis Muthike Njuki; Plaintiff: Salesius Njeru Karuri; Defendant: Co-operative Bank of Kenya Ltd.
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Case 530 of 2006
Procedural Posture
Civil Case / Ruling on Interlocutory Injunction Application
Outcome
application dismissed with costs to the defendant
Legal Topics
Performance Bonds, Injunctive Relief, Bank Guarantees, Contract Enforcement, Security Realization
Source Language
en
Banking and Finance Civil Procedure Performance Bonds Injunctive Relief Bank Guarantees Contract Enforcement Security Realization

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 4 Party arguments 2 Amounts and remedies 5
Sign in to unlock

Parties

Francis Muthike Njuki

Plaintiff

Salesius Njeru Karuri

Plaintiff

Co-operative Bank of Kenya Ltd.

Defendant

Procedural Posture

Civil Case / Ruling on Interlocutory Injunction Application

  1. 1 Whether the plaintiffs have established a prima facie case with a probability of success to warrant the grant of an interlocutory injunction.
  2. 2 Whether the plaintiffs would suffer irreparable harm not compensatable by damages if the injunction is not granted.
  3. 3 Whether the conduct of the plaintiffs disentitles them to equitable relief of injunction.

Ratio Decidendi

The court found that the plaintiffs failed to establish a prima facie case with a probability of success, as the performance bond was valid until the certificate of completion and the defendant was obliged to pay upon demand by KPLC. The plaintiffs had benefited from the bond and could not challenge its validity on grounds of execution or stamping after the fact. The court further held that any injury suffered by the plaintiffs could be adequately compensated by damages, as the charged properties were commodities for sale by virtue of the plaintiffs' own actions. The plaintiffs' conduct, having benefited from the facilities and not settled their obligations, was unworthy of equitable...

Court Disposition

application dismissed with costs to the defendant

Orders

  • The plaintiffs' application for interlocutory injunction is dismissed.
  • The plaintiffs shall pay the costs of the application to the defendant.