[2012] KEHC 168 (KLR)
The court found that the defendant failed to demonstrate sufficient cause for payment by the proposed instalments, as previously agreed instalments were not honoured and no payment had been made since April 2012. The defendant's financial incapacity was not adequately proven, as one bank statement was not in the defendant's name and the other covered only a brief period. The court, balancing the rights of both parties, exercised its discretion to allow payment of the decretal amount in four equal consecutive instalments over twelve months, with the first instalment due by 20th January 2013 and subsequent instalments every third month. In default of any instalment, execution would issue....
- Citation
- [2012] KEHC 168 (KLR)
- Parties
- Plaintiff: Freight Forwarders Ltd; Defendant: Elsek & Elsek (K) Ltd
- Court
- High Court
- Court Station
- High Court at Mombasa
- Jurisdiction
- Kenya
- Judgment Date
- 19 December 2012
- Case Number
- Civil Case 56 of 2012
- Procedural Posture
- Civil Case / Ruling on Application for Stay of Execution and Payment by Instalments
- Outcome
- Application partially allowed; payment by instalments granted on strict terms; costs to plaintiff.
- Judges
- RM Mwongo
- Legal Topics
- Stay of Execution, Payment by Instalments, Judgment Debtor Applications
- Source Language
- English
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Freight Forwarders Ltd
Plaintiff
Elsek & Elsek (K) Ltd
Defendant
Procedural Posture
Civil Case / Ruling on Application for Stay of Execution and Payment by Instalments
Legal Issues
- 1 Whether the judgment debtor has shown sufficient cause to warrant payment of the decretal sum by instalments.
- 2 Whether the court should grant a stay of execution pending payment by instalments.
- 3 What terms, if any, should be imposed for payment of the decretal sum.
Ratio Decidendi
The court found that the defendant failed to demonstrate sufficient cause for payment by the proposed instalments, as previously agreed instalments were not honoured and no payment had been made since April 2012. The defendant's financial incapacity was not adequately proven, as one bank statement was not in the defendant's name and the other covered only a brief period. The court, balancing the rights of both parties, exercised its discretion to allow payment of the decretal amount in four equal consecutive instalments over twelve months, with the first instalment due by 20th January 2013 and subsequent instalments every third month. In default of any instalment, execution would issue....
Court Disposition
Application partially allowed; payment by instalments granted on strict terms; costs to plaintiff.
Orders
- The decretal amount of Kshs. 8,665,944 to be paid in four equal consecutive instalments within twelve months.
- The first instalment to be paid on or before 20th January, 2013; subsequent instalments on the 20th day of every third month thereafter (April, July, October).
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment