[2017] KEHC 6365 (KLR)

[2017] KEHC 6365 (KLR)

The High Court held that it had jurisdiction under Section 7 of the Arbitration Act to entertain an application for interim measures of protection, even where the dispute involved a terminated contract and a public procurement process. However, the applicant failed to demonstrate that the subject matter of the...

Source-derived case information.

Citation
[2017] KEHC 6365 (KLR)
Parties
Applicant: Futureway Limited; Respondent: National Oil Corporation of Kenya
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Miscellaneous Civil Application 550 of 2016
Procedural Posture
Miscellaneous Application / Ruling on Application for Interim Measures of Protection Pending Arbitration
Outcome
application dismissed
Legal Topics
Arbitration Agreements, Interim Measures, Contract Termination, Public Procurement, Injunctive Relief
Source Language
en
Commercial and Corporate Alternative Dispute Resolution Arbitration Agreements Interim Measures Contract Termination Public Procurement Injunctive Relief

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 14 Party arguments 2
Sign in to unlock

Parties

Futureway Limited

Applicant

National Oil Corporation of Kenya

Respondent

Procedural Posture

Miscellaneous Application / Ruling on Application for Interim Measures of Protection Pending Arbitration

  1. 1 Whether the High Court has jurisdiction to grant interim measures of protection pending arbitration in a dispute involving a terminated contract and ongoing public procurement process.
  2. 2 Whether the applicant is entitled to injunctive relief restraining the respondent from awarding a new transport contract pending arbitration.
  3. 3 Whether the subject matter of the arbitration would be rendered nugatory if interim protection is not granted.

Ratio Decidendi

The High Court held that it had jurisdiction under Section 7 of the Arbitration Act to entertain an application for interim measures of protection, even where the dispute involved a terminated contract and a public procurement process. However, the applicant failed to demonstrate that the subject matter of the arbitration—the right to provide transport services under the terminated contract—would be rendered nugatory or beyond the reach of the arbitral tribunal if interim protection was not granted. The court found that the contract had already been terminated, and the applicant's remedy, if any, would lie in damages rather than specific performance or preservation of the contract. The...

Court Disposition

application dismissed

Orders

  • The application dated 1 March 2017 is dismissed.
  • The applicant shall pay the costs of the application to the respondent.