[2019] KEHC 7782 (KLR)

[2019] KEHC 7782 (KLR)

The court found that the Deed of Settlement between the plaintiff and the 2nd defendant was lawful, binding, and intended to settle all claims arising from the construction of market stalls. The principal sum claimed by the plaintiff, less amounts already paid, was not disputed by the 2nd defendant. However, the...

Source-derived case information.

Citation
[2019] KEHC 7782 (KLR)
Parties
Plaintiff: Galexon Kenya Limited; Defendant: Centre for Youth Linkages and Empowerment Programmes; Defendant: County Government of Vihiga; Defendant: Annet Ilamunya & 2 Others (as officials of Mbale Open Air Committee C.B.O)
Court
High Court
Court Station
High Court at Kisumu
Jurisdiction
Kenya
Case Number
Commercial Suit 18 of 2017
Procedural Posture
Commercial Case / Ruling on Quantum and Entitlement to General Damages After Partial Settlement
Outcome
Plaintiff's claim partially succeeds against the 2nd defendant; principal sum, interest, and costs awarded; general damages denied.
Judges
TW Cherere
Legal Topics
Breach of Contract, Settlement Agreements, Quantum of Damages, Interest Awards
Source Language
en
Commercial and Corporate Civil Procedure Breach of Contract Settlement Agreements Quantum of Damages Interest Awards

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 8 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Galexon Kenya Limited

Plaintiff

Centre for Youth Linkages and Empowerment Programmes

Defendant

County Government of Vihiga

Defendant

Annet Ilamunya & 2 Others (as officials of Mbale Open Air Committee C.B.O)

Defendant

Procedural Posture

Commercial Case / Ruling on Quantum and Entitlement to General Damages After Partial Settlement

  1. 1 Whether the plaintiff is entitled to the claimed sum for construction of market stalls under the Deed of Settlement.
  2. 2 Whether the plaintiff is entitled to general damages for breach of contract against the 2nd defendant.
  3. 3 Whether interest and costs are payable to the plaintiff.

Ratio Decidendi

The court found that the Deed of Settlement between the plaintiff and the 2nd defendant was lawful, binding, and intended to settle all claims arising from the construction of market stalls. The principal sum claimed by the plaintiff, less amounts already paid, was not disputed by the 2nd defendant. However, the court held that general damages for breach of contract are only awardable in exceptional circumstances, such as oppressive or high-handed conduct, which the plaintiff failed to prove against the 2nd defendant. Consequently, the plaintiff was awarded the principal sum (less amounts already paid), interest at court rates from the date of initial demand, and costs, but not general...

Court Disposition

Plaintiff's claim partially succeeds against the 2nd defendant; principal sum, interest, and costs awarded; general damages denied.

Orders

  • Judgment for the plaintiff against the 2nd defendant for Kshs. 21,798,450 less Kshs. 1,000,000 already paid.
  • Interest on the net sum at court rates from 6th June, 2017.