[2013] KEHC 3870 (KLR)

[2013] KEHC 3870 (KLR)

The court found that a contract existed between the parties based on the exchange of proposals and acceptance letters, despite the absence of a formal written agreement. The cost figures in the proposals were treated as estimates, not fixed sums, but later correspondence and payment schedules solidified the...

Source-derived case information.

Citation
[2013] KEHC 3870 (KLR)
Parties
Plaintiff: Genesis Architects Limited; Defendant: Jitegemee Trust Limited
Court
High Court
Court Station
High Court at Nairobi (Milimani Law Courts)
Jurisdiction
Kenya
Case Number
Civil Case 194 of 2009
Procedural Posture
Civil Case / Judgment
Outcome
Judgment for both plaintiff and defendant in part; each awarded substantiated damages; no order as to costs.
Judges
JB Havelock
Legal Topics
Breach of Contract, Building Contracts, Special Damages, Professional Negligence, Quantum of Damages
Source Language
en
Commercial and Corporate Civil Procedure Breach of Contract Building Contracts Special Damages Professional Negligence Quantum of Damages

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 8 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Genesis Architects Limited

Plaintiff

Jitegemee Trust Limited

Defendant

Procedural Posture

Civil Case / Judgment

  1. 1 Whether there was a valid contract between the parties for architectural and construction services.
  2. 2 Whether the plaintiff or defendant breached the contract and the consequences thereof.
  3. 3 Whether the plaintiff is entitled to special damages for unpaid invoices and loss of benefits.

Ratio Decidendi

The court found that a contract existed between the parties based on the exchange of proposals and acceptance letters, despite the absence of a formal written agreement. The cost figures in the proposals were treated as estimates, not fixed sums, but later correspondence and payment schedules solidified the contractual amounts. The plaintiff was entitled to payment for work done and consultancy fees up to the point of termination, but not for interest as there was no contractual basis for such a claim. The defendant was entitled to damages for incomplete and defective work, but only to the extent supported by the expert's valuation, not the full counterclaim amount. Both parties failed to...

Court Disposition

Judgment for both plaintiff and defendant in part; each awarded substantiated damages; no order as to costs.

Orders

  • Judgment for the plaintiff in the sum of KES 979,239.
  • Judgment for the defendant on the counterclaim in the sum of KES 1,124,693.70.