[2023] KEELC 22058 (KLR)

[2023] KEELC 22058 (KLR)

The court found that the appellant had not demonstrated substantial loss warranting a stay of execution, as he was already restrained from entering or constructing on the suit land by an interlocutory order. The only potential loss identified was the demolition of the perimeter wall. The appellant failed to address...

Source-derived case information.

Citation
[2023] KEELC 22058 (KLR)
Parties
Appellant: Ahmed Chege Gikera; Respondent: Lucy Wanjiru Solomon
Court
Environment and Land Court
Court Station
Environment and Land Court at Thika
Jurisdiction
Kenya
Case Number
Environment and Land Appeal E044 of 2023
Procedural Posture
Environment and Land Appeal / Ruling on Application for Stay of Execution Pending Appeal
Outcome
Conditional stay of execution granted, limited to preservation of perimeter wall and existing structures, subject to deposit of Kshs 280,400 within 30 days.
Judges
BM Eboso
Legal Topics
Stay of Execution, Security for Costs, Ownership of Land, Eviction Orders
Source Language
en
Land and Property Civil Procedure Stay of Execution Security for Costs Ownership of Land Eviction Orders

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 1 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

Ahmed Chege Gikera

Appellant

Lucy Wanjiru Solomon

Respondent

Procedural Posture

Environment and Land Appeal / Ruling on Application for Stay of Execution Pending Appeal

  1. 1 Whether the appellant has satisfied the criteria for grant of an order of stay of execution pending appeal.
  2. 2 Whether the application for stay was brought without unreasonable delay.
  3. 3 Whether the appellant has provided adequate security for the due performance of the decree.

Ratio Decidendi

The court found that the appellant had not demonstrated substantial loss warranting a stay of execution, as he was already restrained from entering or constructing on the suit land by an interlocutory order. The only potential loss identified was the demolition of the perimeter wall. The appellant failed to address the requirement for security for due satisfaction of the decree, despite being ordered to pay general damages and costs. The application for stay was not brought with inordinate delay, considering the trial court had already granted a 90-day stay. The court therefore granted a conditional stay limited to preservation of the perimeter wall and any other existing structure,...

Court Disposition

Conditional stay of execution granted, limited to preservation of perimeter wall and existing structures, subject to deposit of Kshs 280,400 within 30 days.

Orders

  • Subject to the appellant depositing Kshs 280,400 in court within 30 days, there shall be a stay of execution of the decree in relation to demolition of the perimeter wall and any other structure erected on land parcel number Ruiru/Kiu Block 2/4793.
  • The order of stay of execution shall lapse upon disposal of the appeal.