[2010] KEHC 3578 (KLR)

[2010] KEHC 3578 (KLR)

The court found that the defendant's own actions—engaging other contractors, interfering with the plaintiff's employees, and withholding funds—frustrated the plaintiff's ability to complete the contract. The defendant's application to vary the injunction was made only after realizing the consequences of its conduct,...

Source-derived case information.

Citation
[2010] KEHC 3578 (KLR)
Parties
Plaintiff: Githambo General Contractors; Defendant: Kay Construction Co. Ltd.
Court
High Court
Court Station
High Court at Nyeri
Jurisdiction
Kenya
Case Number
Civil Case 135 of 2009
Procedural Posture
Civil Case / Ruling on Interlocutory Application
Outcome
application dismissed with costs to the plaintiff
Legal Topics
Injunctions, Variation of Orders, Contractual Obligations, Sub Contracting, Breach of Contract
Source Language
en
Civil Procedure Commercial and Corporate Injunctions Variation of Orders Contractual Obligations Sub Contracting Breach of Contract

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 2 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Githambo General Contractors

Plaintiff

Kay Construction Co. Ltd.

Defendant

Procedural Posture

Civil Case / Ruling on Interlocutory Application

  1. 1 Whether the injunction order issued on 13th October 2009 should be varied to allow both parties to jointly perform the hand packing of stones pending determination of the suit.
  2. 2 Whether the defendant is entitled to equitable relief given its conduct in relation to the contract and court orders.
  3. 3 Whether the defendant's actions amounted to frustration of the plaintiff's ability to perform the contract.

Ratio Decidendi

The court found that the defendant's own actions—engaging other contractors, interfering with the plaintiff's employees, and withholding funds—frustrated the plaintiff's ability to complete the contract. The defendant's application to vary the injunction was made only after realizing the consequences of its conduct, and thus it approached the court with unclean hands. Granting the variation would amount to the court redrawing the parties' contract, which is not its function. The court held that the defendant was not entitled to equitable relief and dismissed the application, reaffirming the binding nature of the original contract and the prior injunction.

Court Disposition

application dismissed with costs to the plaintiff

Orders

  • The Notice of Motion dated 20th November 2009 is dismissed with costs to the plaintiff.