[2009] KEHC 1648 (KLR)

[2009] KEHC 1648 (KLR)

The court found that the plaintiff had established a prima facie case with a probability of success, as the defendant did not deny the plaintiff was subcontracted and had invested resources in the project. The court determined that the loss the plaintiff would suffer if the injunction was denied would be so...

Source-derived case information.

Citation
[2009] KEHC 1648 (KLR)
Parties
Plaintiff: Githambo General Contractors; Defendant: Kay Construction Company Ltd
Court
High Court
Court Station
High Court at Nyeri
Jurisdiction
Kenya
Case Number
Civil Case 135 of 2009
Procedural Posture
Civil Case / Ruling on Interlocutory Injunction Application
Outcome
Application for temporary injunction granted in terms of prayer 2 with costs to the plaintiff.
Judges
JK Sergon
Legal Topics
Injunctions, Breach of Contract, Subcontractor Rights, Irreparable Harm
Source Language
en
Commercial and Corporate Civil Procedure Injunctions Breach of Contract Subcontractor Rights Irreparable Harm

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 1 Party arguments 2
Sign in to unlock

Parties

Githambo General Contractors

Plaintiff

Kay Construction Company Ltd

Defendant

Procedural Posture

Civil Case / Ruling on Interlocutory Injunction Application

  1. 1 Whether the plaintiff has established a prima facie case with a probability of success for the grant of a temporary injunction.
  2. 2 Whether the plaintiff would suffer irreparable loss not compensable by damages if the injunction is denied.
  3. 3 Whether the balance of convenience favours granting the injunction.

Ratio Decidendi

The court found that the plaintiff had established a prima facie case with a probability of success, as the defendant did not deny the plaintiff was subcontracted and had invested resources in the project. The court determined that the loss the plaintiff would suffer if the injunction was denied would be so substantial and unquantifiable that damages would not be an adequate remedy. The defendant failed to quantify the potential loss, and the balance of convenience favoured the plaintiff. Consequently, the court granted the temporary injunction restraining the defendant from interfering with the plaintiff's subcontract or engaging others for the same work until the determination of the...

Court Disposition

Application for temporary injunction granted in terms of prayer 2 with costs to the plaintiff.

Orders

  • The defendant, by itself, agents or servants, is restrained by a temporary injunction from interfering with the plaintiff’s subcontract of hand packing stones and from engaging other persons in the subcontract of hand packing stones other than the plaintiff in the construction of St. Marys – Nyakahura – Kiamara –...
  • Costs of the application awarded to the plaintiff.