[2019] KEHC 1336 (KLR)
The court found that the applicant demonstrated a real threat to the subject matter of the arbitration—the incomplete building—due to exposure to the elements and risk of financial loss. The existence of an arbitration agreement was not in dispute, and both parties were prepared to proceed to arbitration. The court held that interim measures of protection were necessary to preserve the property and allow the applicant to mitigate losses, as the contract had already been terminated and no works were ongoing. The respondent's claim to a lien over the site was rejected as unsupported by law in building contracts. The court concluded that the appropriate interim relief was to restrain the...
- Citation
- [2019] KEHC 1336 (KLR)
- Parties
- Plaintiff: Globe Developers Limited; Defendant: Mark Properties Limited
- Court
- High Court
- Court Station
- High Court at Nairobi (Milimani Law Courts)
- Jurisdiction
- Kenya
- Judgment Date
- 14 October 2019
- Case Number
- Environment & Land Case 273 of 2019
- Procedural Posture
- Chamber Summons / Ruling on Interim Measures Pending Arbitration
- Outcome
- Application allowed; interim measures of protection granted; matter referred to arbitration; costs to respondent.
- Legal Topics
- Building Contracts, Interim Measures, Arbitration Clauses, Termination of Contracts, Site Possession, Contractual Disputes
- Source Language
- English
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Globe Developers Limited
Plaintiff
Mark Properties Limited
Defendant
Procedural Posture
Chamber Summons / Ruling on Interim Measures Pending Arbitration
Legal Issues
- 1 Whether the applicant is entitled to interim measures of protection pending arbitration.
- 2 Whether the subject matter of the arbitration (the construction site and incomplete building) is under threat warranting court intervention.
- 3 Whether the respondent is entitled to retain possession of the site as a lien for unpaid dues.
Ratio Decidendi
The court found that the applicant demonstrated a real threat to the subject matter of the arbitration—the incomplete building—due to exposure to the elements and risk of financial loss. The existence of an arbitration agreement was not in dispute, and both parties were prepared to proceed to arbitration. The court held that interim measures of protection were necessary to preserve the property and allow the applicant to mitigate losses, as the contract had already been terminated and no works were ongoing. The respondent's claim to a lien over the site was rejected as unsupported by law in building contracts. The court concluded that the appropriate interim relief was to restrain the...
Court Disposition
Application allowed; interim measures of protection granted; matter referred to arbitration; costs to respondent.
Orders
- The defendant, its servants, agents or otherwise are restrained from interfering with the plaintiff’s possession and construction on LR 209/4904 Riverside Drive pending arbitration.
- The Officer in Charge of Kileleshwa Police Station to enforce compliance and keep the peace.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment