The court found that the plaintiff's demand on the performance bond was made within the bond's validity period, satisfying the condition precedent for liability. The variations to the contract cited by the defendant were within the scope of Clause 30, which expressly permitted such changes with architect approval,...

Source-derived case information.

Citation
[2020] KEHC 10286 (KLR)
Parties
Plaintiff: Globe Developers Limited; Defendant: Mayfair Insurance Company Limited
Court
High Court
Court Station
High Court at Nairobi (Milimani Law Courts)
Jurisdiction
Kenya
Case Number
Civil Case E186 of 2020
Procedural Posture
Civil Case / Ruling on Summary Judgment and Striking Out Applications
Outcome
summary judgment for plaintiff; defendant's application dismissed
Judges
DAS Majanja
Legal Topics
Performance Bonds, Summary Judgment, Contract Variations, Surety Liability, Arbitration and Bonds
Source Language
en
Commercial and Corporate Civil Procedure Performance Bonds Summary Judgment Contract Variations Surety Liability Arbitration and Bonds

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 13 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Globe Developers Limited

Plaintiff

Mayfair Insurance Company Limited

Defendant

Procedural Posture

Civil Case / Ruling on Summary Judgment and Striking Out Applications

  1. 1 Whether the plaintiff is entitled to summary judgment for the amount claimed under the performance bond.
  2. 2 Whether the defendant is discharged from liability under the bond due to alleged contract variations.
  3. 3 Whether the existence of pending arbitration proceedings between the plaintiff and contractor affects the defendant's liability under the bond.

Ratio Decidendi

The court found that the plaintiff's demand on the performance bond was made within the bond's validity period, satisfying the condition precedent for liability. The variations to the contract cited by the defendant were within the scope of Clause 30, which expressly permitted such changes with architect approval, and did not amount to material alterations discharging the surety. The doctrine of utmost good faith does not apply to performance bonds, and there was no contractual or legal obligation for the plaintiff to notify the defendant of the variations. The bond is an independent contract, and the existence of arbitration proceedings between the plaintiff and the contractor does not...

Court Disposition

summary judgment for plaintiff; defendant's application dismissed

Orders

  • The defendant's application dated 6th August 2020 is dismissed with costs to the plaintiff.
  • The plaintiff's application dated 25th June 2020 is allowed; judgment is entered for the plaintiff against the defendant for Kshs. 143,430,335.00.