[2022] KECA 812 (KLR)

[2022] KECA 812 (KLR)

The Court of Appeal held that the issuance of the final certificate by the architect, which was not challenged within 14 days as required by Clause 30.7 of the contract, rendered the sums certified as due to the respondent final and conclusive. No dispute or difference existed between the parties capable of...

Source-derived case information.

Citation
[2022] KECA 812 (KLR)
Parties
Appellant: Golden Jubilee Limited; Respondent: Misty Jadva Parbat & Company Limited
Court
Court of Appeal
Court Station
Court of Appeal at Nairobi
Jurisdiction
Kenya
Case Number
Civil Appeal 8 of 2018
Procedural Posture
Civil Appeal / Judgment on Appeal From High Court Summary Judgment and Stay Application
Outcome
appeal dismissed; High Court summary judgment and orders upheld
Judges
HM Okwengu, K M'Inoti, KI Laibuta
Legal Topics
Construction Contracts, Arbitration Clauses, Summary Judgment, Liquidated Damages, Set Off and Counterclaim
Source Language
en
Commercial and Corporate Civil Procedure Construction Contracts Arbitration Clauses Summary Judgment Liquidated Damages Set Off and Counterclaim

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 6 Party arguments 2 Amounts and remedies 6
Sign in to unlock

Parties

Golden Jubilee Limited

Appellant

Misty Jadva Parbat & Company Limited

Respondent

Procedural Posture

Civil Appeal / Judgment on Appeal From High Court Summary Judgment and Stay Application

  1. 1 Whether a dispute or difference existed between the parties requiring submission to arbitration under Clause 40 of the contract.
  2. 2 Whether the appellant's alleged set-off or counterclaim was due and recoverable from the respondent in the suit or proposed arbitral proceedings.

Ratio Decidendi

The Court of Appeal held that the issuance of the final certificate by the architect, which was not challenged within 14 days as required by Clause 30.7 of the contract, rendered the sums certified as due to the respondent final and conclusive. No dispute or difference existed between the parties capable of reference to arbitration after the final certificate was issued and not contested in the prescribed manner. The appellant's claim for set-off or counterclaim for liquidated and ascertained damages was not supported by any architect's certificate, as required by Clauses 22 and 30, and thus was not recoverable either in the suit or in proposed arbitral proceedings. The appellant's mere...

Court Disposition

appeal dismissed; High Court summary judgment and orders upheld

Orders

  • The appellant's appeal is dismissed.
  • The Ruling and order of the High Court (Fred A. Ochieng, J) delivered on 8th June 2016 is upheld.