[2017] KEHC 7092 (KLR)

[2017] KEHC 7092 (KLR)

The court found that the parties entered into a written construction agreement for a villa at a contractual sum of 125,000 Euros, and subsequently entered into an oral agreement for additional works (swimming pool and garage) at 25,000 Euros. The defendant was paid 85,000 Euros, leaving a balance of 40,000 Euros for...

Source-derived case information.

Citation
[2017] KEHC 7092 (KLR)
Parties
Plaintiff: Gona Jacob Janja; Plaintiff: Itavignola Anna; Defendant: Luigi Gospedini; Plaintiff: Jambo Imobiliare Ltd; Defendant: Anna Itavignola
Court
High Court
Court Station
High Court at Malindi
Jurisdiction
Kenya
Case Number
Civil Case 9 of 2014
Procedural Posture
Civil Case / Judgment
Outcome
Plaintiffs' suit dismissed; defendant's counterclaim allowed.
Judges
SJ Chitembwe
Legal Topics
Breach of Contract, Construction Agreements, Counterclaims, Oral and Written Contracts
Source Language
en
Commercial and Corporate Civil Procedure Breach of Contract Construction Agreements Counterclaims Oral and Written Contracts

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 1 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Gona Jacob Janja

Plaintiff

Itavignola Anna

Plaintiff

Luigi Gospedini

Defendant

Jambo Imobiliare Ltd

Plaintiff

Anna Itavignola

Defendant

Procedural Posture

Civil Case / Judgment

  1. 1 Whether the defendant proved its counterclaim for unpaid construction sums.
  2. 2 Whether the plaintiffs established their claim for reimbursement and special damages based on breach of contract.
  3. 3 Whether the oral agreement for additional works (swimming pool and garage) was enforceable.

Ratio Decidendi

The court found that the parties entered into a written construction agreement for a villa at a contractual sum of 125,000 Euros, and subsequently entered into an oral agreement for additional works (swimming pool and garage) at 25,000 Euros. The defendant was paid 85,000 Euros, leaving a balance of 40,000 Euros for the main contract and 25,000 Euros for the additional works, totaling 65,000 Euros. The plaintiffs failed to attend court and did not substantiate their claims for reimbursement or special damages. The defendant's evidence was uncontroverted, and the oral agreement for additional works was supported by the plaintiffs' own admissions. The court dismissed the plaintiffs' suit...

Court Disposition

Plaintiffs' suit dismissed; defendant's counterclaim allowed.

Orders

  • Plaintiffs' suit is dismissed.
  • Defendant's counterclaim is allowed.