[2024] KEHC 10302 (KLR)

[2024] KEHC 10302 (KLR)

The court found that the plaintiff had specifically pleaded and strictly proved its claim for special damages in the sum of Kshs.19,703,474/- by producing undisputed invoices and delivery notes for services rendered. The defendant failed to demonstrate that these invoices had been settled or that nothing was owed....

Source-derived case information.

Citation
[2024] KEHC 10302 (KLR)
Parties
Plaintiff: Great White Investment Limited; Defendant: National Oil Corporation Of Kenya
Court
High Court
Court Station
High Court at Mombasa
Jurisdiction
Kenya
Case Number
Civil Suit E029 of 2021
Procedural Posture
Civil Suit / Judgment
Outcome
Judgment for the plaintiff; counterclaim dismissed.
Judges
F Wangari
Legal Topics
Breach of Contract, Special Damages, Counterclaim Proof, Termination of Contract, Burden of Proof
Source Language
en
Commercial and Corporate Civil Procedure Breach of Contract Special Damages Counterclaim Proof Termination of Contract Burden of Proof

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 6 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

Great White Investment Limited

Plaintiff

National Oil Corporation Of Kenya

Defendant

Procedural Posture

Civil Suit / Judgment

  1. 1 Whether the Plaintiff specifically pleaded and strictly proved special damages in the sum of Kshs.19,703,474/-.
  2. 2 Whether the Plaintiff is entitled to general damages for breach of contract.
  3. 3 What is the order as to costs and interests?

Ratio Decidendi

The court found that the plaintiff had specifically pleaded and strictly proved its claim for special damages in the sum of Kshs.19,703,474/- by producing undisputed invoices and delivery notes for services rendered. The defendant failed to demonstrate that these invoices had been settled or that nothing was owed. The court also found that the defendant's immediate termination of the contract without adhering to the one-month notice requirement was unlawful and amounted to a breach of contract, entitling the plaintiff to general damages. The defendant's counterclaim for Kshs.190,716,876/- was dismissed as it was not strictly proved; the external audit report relied upon was not produced...

Court Disposition

Judgment for the plaintiff; counterclaim dismissed.

Orders

  • Special damages of Kshs.19,703,474/- awarded to the plaintiff with interest at court rates from the date of filing suit until payment in full.
  • General damages for breach of contract assessed at Kshs.3,000,000/- awarded to the plaintiff with interest from the date of judgment until payment in full.