[2025] KEHC 5600 (KLR)
The court found that the plaintiff had proved its case on a balance of probabilities through documentary evidence, including agreements, payment certificates, and demand letters. The defendant, having failed to enter appearance or file a defence, did not contest the claim. The court held that the defendant breached...
Source-derived case information.
- Citation
- [2025] KEHC 5600 (KLR)
- Parties
- Plaintiff: Hekima Kijani Kenya Limited; Defendant: China State Construction Engineering Corporation (Kenya) Limited
- Court
- High Court
- Court Station
- High Court at Kitale
- Jurisdiction
- Kenya
- Case Number
- Civil Case E002 of 2024
- Procedural Posture
- Civil Case / Judgment
- Outcome
- Judgment for the plaintiff as prayed in prayers (a), (b), and (c) of the plaint. Interest on the principal sum at court rates from the date of filing suit until payment in full. Costs to the plaintiff.
- Judges
- RK Limo
- Legal Topics
- Breach of Contract, Equipment Hire Agreements, Payment Certificates, Interest on Debt
- Source Language
- en
Source-derived case record
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Hekima Kijani Kenya Limited
Plaintiff
China State Construction Engineering Corporation (Kenya) Limited
Defendant
Procedural Posture
Civil Case / Judgment
Legal Issues
- 1 Whether the defendant breached the contract entered into with the plaintiff.
- 2 Whether the plaintiff is entitled to the claimed sum of Kshs.70,026,559 for unpaid invoices and certificates.
- 3 Whether the plaintiff is entitled to interest at 5% per annum from 9th July 2019 until payment in full.
Ratio Decidendi
The court found that the plaintiff had proved its case on a balance of probabilities through documentary evidence, including agreements, payment certificates, and demand letters. The defendant, having failed to enter appearance or file a defence, did not contest the claim. The court held that the defendant breached the contract by failing to pay the sums due for the hire of machinery as agreed. The plaintiff was therefore entitled to the sum of Kshs.70,026,559, interest at 5% per annum from 9th July 2019 until payment in full, and costs of the suit. The court further ordered that interest on the principal sum would accrue at court rates from the date of filing suit until payment in full.
Court Disposition
Judgment for the plaintiff as prayed in prayers (a), (b), and (c) of the plaint. Interest on the principal sum at court rates from the date of filing suit until payment in full. Costs to the plaintiff.
Orders
- A declaration that the defendant breached the contract with the plaintiff.
- The defendant shall pay the plaintiff Kshs.70,026,559.
Full Case Text
Judgment text and source record
29 paragraphs
Hekima Kijani Kenya Limited v China State Construction Engineering Corporation (Kenya) Limited (Civil Case E002 of 2024) [2025] KEHC 5600 (KLR) (5 May 2025) (Judgment)
Neutral citation: [2025] KEHC 5600 (KLR)
Republic of Kenya
In the High Court at Kitale
Civil Case E002 of 2024
RK Limo, J
May 5, 2025
Between
Hekima Kijani Kenya Limited
Plaintiff
and
China State Construction Engineering Corporation (Kenya) Limited
Defendant
Judgment
1. The plaintiff herein, Hekima Kijani Kenya Limited vide a plaint herein dated 5th February 2024 filed a claim against the defendant China State Construction Engineering Corporation (K) Limited the defendant herein, for breach of contract and prayed for the following reliefs namely;a.A declaration that the defendant breached the contract it entered with the plaintiff.b.An order directing the defendant to pay the plaintiff a sum of Kshs.70,026,559. c.An order directing the defendant to pay the plaintiff interests of the principal sum at the rate of 5% per annum from 9th July 2019 until payment is made in full.d.Interest on (b) and (c) above at commercial rates from the date of filing this suit until payment is made in full.e.Costs of the suit.
2. The plaintiff through Victoriah Mukiiri, a representative of the plaintiff’s company testified that the defendant had been engaged by Kenya National Highway Authority (KENHA) for the construction of Kapchorwa Multinational Uganda-Kenya, Kapchorwa-Suam-Kitale and Bypass Eldoret Town Bypass project and upgrading of Endebess Suam-Kitale, Endebess-Suam Road project.
3. It is the plaintiff’s case that on or around 5th September 2018, the defendant entered into an agreement with Konvest Source Ltd wherein the defendant hired the following machinery namely;i.Tipper-Shacman (SX32554DR384R)ii.Sanny Motor Grader (SAG200-5)iii.Excavator (SY-220C)
4. The plaintiff claims that pursuant to the contract between the plaintiff and the said Konvest Source Limited, the defendant owed the latter Kshs.28,308,074. 03/- and that Konvest Source Ltd issued instructions to the defendant to remit the said sum directly to the plaintiff. The plaintiff states that the defendant received and acknowledged those said instructions.
5. The plaintiff claims that further to the above arrangements KONVEST SOURCE LIMITED transferred its rights over the machinery to the plaintiff who in turn executed a new agreement with the defendant vide agreement dated 1st September 2019 and on the basis of that agreement, the defendant retained the possession and use of the machinery in the said road project.
6. The plaintiff claims that it together with the defendant jointly prepared payment certificates that were verified and approved by both parties making them due for payment upon issuance of requisite invoice and ETR. The plaintiff states that despite raising invoices and ETR for payment, the defendant blatantly failed, neglected and/or ignored to settle the invoices as they fell due.
7. It is the plaintiff’s case that on 15/2/2022, it together with the defendant jointly raised final payment certificate in the sum of Kshs.48,218, 485. 02/- which was due and owing and that once the final payment certificate was raised the defendant had the immediate obligation to settle the sum or in the very least commit to settle the sum within a specified period.
8. The plaintiff claims the defendant owes it Kshs.48,218,485. 05 as per final payment issued on 22/2/2022 and Kshs.28,308,074. 03 which it was to receive on behalf of KONVEST which in total was Kshs.76,526,559/-.
9. The plaintiff states that out of the above total amount owing, the defendant only paid Kshs.6,500,000/- on diverse dates between 19/5/2020 and 31/3/2023.
10. The plaintiff claims that despite extensive indulgence extended to the defendant and demands made the defendant has been reluctant to pay occasioning it loss.
11. It further claims that the outstanding is attracting agreed interest at 5% per annum from the date it was due till payment in full.
12. The plaintiff tendered the following documents to support its case against the defendant;i.Letter of authority – Pexhibit 1ii.Agreement for Hire of Equipment dated 5/9/2018- PExhibit 2iii.Interim payment certificate dated 7/7/2019 – PExhibit 3iv.Interim payment certificate dated 7/9/2019 – Pexhibit 4v.Agreement for Hire of Equipment – Pexhibit 5vi.Instruction for payment dated 2/9/2019 – Pexhibit 6vii.Final payment certificate dated 15/2/2022 – Pexhibit 7viii.Demand letter dated 20/9/2023 – Pexhibit 8
13. The plaintiff prayed for judgment for the total sum owed which it claimed was Kshs.70,026,559/- plus interests at 5% as per the agreement.
14. The defendant despite service did not defend this suit or enter any appearance. The plaintiff’s claim is therefore uncontested and in view of the documents tendered in support of its claim this court finds that the plaintiff has proved its case to the required standard. Consequently this court enters judgment against the defendant in terms or prayer (1) (2) and (3) in the plaint. The plaintiff will get interests of (2) above at court rates from the date of filing suit until the payment is made in full. The defendant will also pay costs of this suit to the plaintiff.
DELIVERED, DATED AND SIGNED AT KITALE THIS 5TH DAY OF MAY , 2025. HON JUSTICE R.K. LIMOKITALE HIGH COURTJudgment delivered in open courtIn the presence of;Sundwa holding brief for Okulo for plaintiffNo appearance for defendantsCourt assistants- Duke/Chemosop